613 W WOODLAWN AVE 90291

Certificate Information: 613 W WOODLAWN AVE 90291

Application / Permit
24010-10000-00498
Plan Check / Job No.
B24LA02387
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(ePLAN) New detached 2-story accessory dwelling per LAMC 12.22 A.33(b)(1). All work per engineer details.
Permit Issued
Issued on 9/29/2025
Issuing Office
Metro
Current Status
Issued on 9/29/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/11/2024 APPLICANT
Assigned to Plan Check Engineer 2/15/2024 VICTOR CHEN
Corrections Issued 2/17/2024 VICTOR CHEN
Quality Review Completed 3/1/2024 HAMID REZAEI
Applicant returned to address corrections 7/5/2024 VICTOR CHEN
Applicant returned to address corrections 6/3/2025 VICTOR CHEN
Applicant returned to address corrections 9/17/2025 VICTOR CHEN
Plan Check Approved 9/18/2025 VICTOR CHEN
Issued 9/29/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 3/27/2024 VLADIMIR ARUTYUNYAN
Eng Process Fee Ord 176,300 Cleared 3/27/2024 VLADIMIR ARUTYUNYAN
Sewer availability Cleared 3/27/2024 VLADIMIR ARUTYUNYAN
Disturb/Remove Protected Trees Cleared 7/19/2024 VICTOR CHEN
Specific Plan Cleared 8/7/2024 FREDDY GARCIA
Specific Plan Cleared 8/7/2024 FREDDY GARCIA
Low Impact Development (LID) Cleared 10/26/2024 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 11/7/2024 ANTHONY MAINEZ
Coastal Zone Cleared 9/5/2025 MAIRA SANCHEZ
Specific Plan Cleared 9/5/2025 MAIRA SANCHEZ

Contact Information

Contractor Silverleaf Construction; Lic. No.: 637190-B 11035 LEOLANG AVE      SUNLAND, CA 91040
Engineer Paniagua,, Cristobal; Lic. No.: C72894 5956 WEST BLVD      LOS ANGELES, CA 90043

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

HVAC-Final 7/23/2026    Time Frame: 9-11

Inspection Request History

PLUMBING-Rough 11/13/2025 Partial Approval JESUS RODRIGUEZ
Footing/Foundation/Slab 11/26/2025 Approved WILBER ROSALES
Floor/Roof Diaphrgm/Shear Wall 12/17/2025 Corrections Issued TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 1/28/2026 Partial Approval RUBEN RIVAS
ELECTRICAL-Rough 2/17/2026 Approved DAKOTA LOW
Interior/Exterior Lathing 2/17/2026 Not Ready for Inspection DAKOTA LOW
PLUMBING-Rough 2/17/2026 Corrections Issued DAKOTA LOW
Interior/Exterior Lathing 3/11/2026 Approved RUBEN RIVAS
BUILDING-Rough-Frame 3/16/2026 Not Ready for Inspection MICHAEL ALLEN
HVAC-Rough 3/16/2026 Approved MICHAEL ALLEN
Verify Sprinkler Sign Off 3/16/2026 Corrections Issued MICHAEL ALLEN
BUILDING-Rough-Frame 3/27/2026 Approved DAKOTA LOW
PLUMBING-Rough 3/27/2026 Approved DAKOTA LOW
Verify Sprinkler Sign Off 3/27/2026 Approved DAKOTA LOW
Insulation 4/7/2026 Approved BOBBY KEY
Special/Order Compliance 4/7/2026 Partial Inspection TEMISTOCLES CAAL
Drywall Nailing 4/13/2026 Approved DAKOTA LOW
Interior/Exterior Lathing 4/21/2026 Approved DAKOTA LOW
ELECTRICAL-Final 6/9/2026 Approved EUGENE CASSIDY
Final 6/9/2026 Corrections Issued EUGENE CASSIDY
PLUMBING-Final 6/9/2026 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 6/9/2026 SGSOV Not Ready EUGENE CASSIDY
Service/Power Release 6/9/2026 Not Ready for Inspection EUGENE CASSIDY
Smoke Detectors 6/9/2026 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 7/1/2026 SGSOV Not Ready DAKOTA LOW