5857 1/4-1/2 E BURWOOD AVE 90042
Certificate Information: 5857 1/4-1/2 E BURWOOD AVE 90042
- Application / Permit
- 24010-10000-00491
- Plan Check / Job No.
- B24LA02355
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED ONE STORY DETACHED 914SF ADU #1 AND 935 SF ADU #2.
- Permit Issued
- Issued on 4/24/2024
- Issuing Office
- Current Status
- CofO Issued on 12/3/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/8/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/15/2024 | JOE VO |
| Corrections Issued | 2/17/2024 | JOE VO |
| Quality Review Completed | 2/20/2024 | GARO TELMI |
| Plan Check Approved | 4/24/2024 | JOE VO |
| Issued | 4/24/2024 | APPLICANT |
| CofO in Progress | 11/25/2024 | ALIZAH MAYAGOITIA |
| Permit Finaled | 12/3/2024 | DEROLD HAUFF |
| CofO Issued | 12/3/2024 | DEROLD HAUFF |
| Permit Finaled | 12/3/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/5/2024 | DAVID LOPEZ |
| Grading Pre-Inspection | Cleared | 3/6/2024 | SERGIO VALENZUELA |
| Eng Process Fee Ord 176,300 | Cleared | 3/20/2024 | DAVID LOPEZ |
| Sewer availability | Cleared | 3/20/2024 | DAVID LOPEZ |
| Hydrant and Access approval | Cleared | 3/25/2024 | KURT CORRAL |
| Low Impact Development (LID) | Cleared | 4/8/2024 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 4/12/2024 | JUSTIN BICOL |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/20/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 6/20/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Excavation/Setback/Form/Re-Bar | 6/24/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 6/24/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Excavation/Setback/Form/Re-Bar | 6/26/2024 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 7/25/2024 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 7/25/2024 | Approved | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/25/2024 | Approved | CRAIG VAUGHAN |
| Green Building Rough | 7/25/2024 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 7/25/2024 | Corrections Issued | CRAIG VAUGHAN |
| PLUMBING-Rough | 7/25/2024 | Approved | CRAIG VAUGHAN |
| Verify Sprinkler Sign Off | 7/25/2024 | Approved | CRAIG VAUGHAN |
| Insulation | 7/30/2024 | Approved | ANTHONY RAMOS |
| Drywall Nailing | 8/2/2024 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 8/2/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 8/19/2024 | Approved | ALEX COLIN |
| Shower Pan | 8/19/2024 | Approved | ALEX COLIN |
| Underground Mechanical | 8/30/2024 | Approved | LUIS CASTRO |
| Final | 11/5/2024 | Conditional Approval | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 11/5/2024 | Approved | ALIZAH MAYAGOITIA |
| Green Building Final | 11/5/2024 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 11/5/2024 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Service/Power Release | 11/5/2024 | Approved | ALIZAH MAYAGOITIA |
| Smoke Detectors | 11/5/2024 | Approved | ALIZAH MAYAGOITIA |
| Final | 11/22/2024 | OK to Issue CofO | ALIZAH MAYAGOITIA |