5044 N LOLETA AVE 90041

Certificate Information: 5044 N LOLETA AVE 90041

Application / Permit
24010-10000-00468
Plan Check / Job No.
B24LA02185
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
E-plan. Convert existing detached 2-car garage to ADU per State Law. NFPA 13D throughout ADU.
Permit Issued
Issued on 7/9/2024
Issuing Office
Current Status
CofO Issued on 2/14/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/11/2024 APPLICANT
Assigned to Plan Check Engineer 2/14/2024 MINA HABILI
Corrections Issued 2/15/2024 MINA HABILI
Applicant returned to address corrections 6/5/2024 ALEXANDER JOO
Plan Check Approved 6/24/2024 MINA HABILI
Issued 7/9/2024 APPLICANT
CofO in Progress 2/13/2025 BRENDAN MORELLI
Permit Finaled 2/14/2025 DEROLD HAUFF
CofO Issued 2/14/2025 DEROLD HAUFF
Permit Finaled 2/14/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/24/2024 CELINA MORENO
Sewer availability Cleared 3/24/2024 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 3/27/2024 JUSTIN BICOL
Grading Pre-Inspection Cleared 6/5/2024 LANNY MERRICK

Contact Information

Contractor Owner-Builder       ,
Engineer Tamu,, O C; Lic. No.: C29787 P O BOX 17083      LONG BEACH, CA 90807

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 8/2/2024 Approved CRAIG VAUGHAN
Footing/Foundation/Slab 9/4/2024 Partial Approval ROY SPAULDING
Footing/Foundation/Slab 9/12/2024 Approved ROY SPAULDING
BUILDING-Rough-Frame 10/29/2024 Approved ROY SPAULDING
ELECTRICAL-Rough 10/29/2024 Approved ROY SPAULDING
Floor/Roof Diaphrgm/Shear Wall 10/29/2024 Approved ROY SPAULDING
Green Building Rough 10/29/2024 Approved ROY SPAULDING
HVAC-Rough 10/29/2024 Approved ROY SPAULDING
PLUMBING-Rough 10/29/2024 Approved ROY SPAULDING
Verify Sprinkler Sign Off 10/29/2024 Approved ROY SPAULDING
Insulation 10/31/2024 Approved ROY SPAULDING
Shower Pan 10/31/2024 Approved ROY SPAULDING
Drywall Nailing 11/4/2024 Approved ROY SPAULDING
Interior/Exterior Lathing 11/4/2024 Approved ROY SPAULDING
Interior/Exterior Lathing 11/14/2024 Approved ROY SPAULDING
ELECTRICAL-Final 1/23/2025 Corrections Issued BRENDAN MORELLI
HVAC-Final 1/23/2025 Corrections Issued BRENDAN MORELLI
PLUMBING-Final 1/23/2025 Corrections Issued BRENDAN MORELLI
ELECTRICAL-Final 2/12/2025 Approved BRENDAN MORELLI
Final 2/12/2025 OK to Issue CofO BRENDAN MORELLI
Green Building Final 2/12/2025 Approved BRENDAN MORELLI
HVAC-Final 2/12/2025 Approved BRENDAN MORELLI
PLUMBING-Final 2/12/2025 Approved BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 2/12/2025 SGSOV Not Required BRENDAN MORELLI
Smoke Detectors 2/12/2025 Approved BRENDAN MORELLI
Service/Power Release 2/13/2025 Approved BRENDAN MORELLI