860 E 112TH ST 90059

Certificate Information: 860 E 112TH ST 90059

Application / Permit
24010-10000-00465
Plan Check / Job No.
B24LA02179
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
E-PLAN. NEW 2-STORY DUPLEX W/ ATTACHED 2-CAR GARAGE
Permit Issued
Issued on 6/18/2024
Issuing Office
Current Status
CofO Corrected on 1/7/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/7/2024 APPLICANT
Assigned to Plan Check Engineer 2/8/2024 FARSHAD ALIMOHAMADI
Corrections Issued 2/12/2024 FARSHAD ALIMOHAMADI
Quality Review Completed 3/8/2024 CAROLYNN NEPOMUCENO
Applicant returned to address corrections 5/25/2024 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 6/6/2024 FARSHAD ALIMOHAMADI
Plan Check Approved 6/11/2024 FARSHAD ALIMOHAMADI
Issued 6/18/2024 APPLICANT
CofO in Progress 11/26/2024 ANTHONY EGSON
Re-Activate Permit 1/7/2025 ANSON MAGLASANG
CofO Issued-Status Void 1/7/2025 ANSON MAGLASANG
Permit Finaled-Status Void 1/7/2025 ANSON MAGLASANG
Permit Finaled 1/7/2025 ANSON MAGLASANG
CofO Corrected 1/7/2025 ANSON MAGLASANG
Permit Finaled 1/7/2025 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 3/16/2024 CELINA MORENO
Permit Cleared 3/16/2024 CELINA MORENO
Low Impact Development (LID) Cleared 3/19/2024 LUIS CRUZ
Eng Process Fee Ord 176,300 Cleared 3/21/2024 CELINA MORENO
Roof/Waste drainage to street Cleared 3/21/2024 CELINA MORENO
Sewer availability Cleared 3/21/2024 CELINA MORENO
Hydrant and Access approval Cleared 4/19/2024 GILBERT URREA
Trees in Parkway Cleared 4/30/2024 ADALBERTO VERA

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: NA81695       ,

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/5/2024 Approved ANSON MAGLASANG
Underground Mechanical 7/16/2024 Partial Approval BEN MOLSTAD
Wood Frame 7/16/2024 Partial Approval BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 7/17/2024 Not Ready for Inspection BEN MOLSTAD
Insulation 7/17/2024 Partial Approval BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 7/18/2024 Partial Approval BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 7/24/2024 Partial Approval BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 8/26/2024 Approved BARRY HACHE
Special/Order Compliance 8/26/2024 Partial Approval BEN MOLSTAD
HVAC-Rough 9/10/2024 Corrections Issued BARRY HACHE
ELECTRICAL-Rough 9/11/2024 Corrections Issued BARRY HACHE
BUILDING-Rough-Frame 9/12/2024 Corrections Issued BARRY HACHE
Green Building Rough 9/12/2024 Approved BARRY HACHE
Verify Sprinkler Sign Off 9/12/2024 Approved BARRY HACHE
Insulation 9/16/2024 Corrections Issued BARRY HACHE
Drywall Nailing 9/20/2024 Approved BARRY HACHE
Interior/Exterior Lathing 9/20/2024 Not Ready for Inspection BARRY HACHE
Interior/Exterior Lathing 9/24/2024 Approved BARRY HACHE
ELECTRICAL-Final 10/24/2024 Not Ready for Inspection ANTHONY EGSON
ELECTRICAL-Final 11/5/2024 Conditional Approval ANTHONY EGSON
HVAC-Final 11/21/2024 Approved ANTHONY EGSON
PLUMBING-Final 11/21/2024 Not Ready for Inspection ANTHONY EGSON
BUILDING-Rough-Frame 11/25/2024 Approved ANTHONY EGSON
ELECTRICAL-Final 11/25/2024 Approved ANTHONY EGSON
Final 11/25/2024 OK to Issue CofO ANTHONY EGSON
Green Building Final 11/25/2024 Approved ANTHONY EGSON
PLUMBING-Final 11/25/2024 Approved ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 11/25/2024 SGSOV Not Required ANTHONY EGSON
Service/Power Release 11/25/2024 Approved ANTHONY EGSON
Smoke Detectors 11/25/2024 Approved ANTHONY EGSON