860 E 112TH ST 90059
Certificate Information: 860 E 112TH ST 90059
- Application / Permit
- 24010-10000-00465
- Plan Check / Job No.
- B24LA02179
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- E-PLAN. NEW 2-STORY DUPLEX W/ ATTACHED 2-CAR GARAGE
- Permit Issued
- Issued on 6/18/2024
- Issuing Office
- Current Status
- CofO Corrected on 1/7/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/7/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/8/2024 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 2/12/2024 | FARSHAD ALIMOHAMADI |
| Quality Review Completed | 3/8/2024 | CAROLYNN NEPOMUCENO |
| Applicant returned to address corrections | 5/25/2024 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 6/6/2024 | FARSHAD ALIMOHAMADI |
| Plan Check Approved | 6/11/2024 | FARSHAD ALIMOHAMADI |
| Issued | 6/18/2024 | APPLICANT |
| CofO in Progress | 11/26/2024 | ANTHONY EGSON |
| Re-Activate Permit | 1/7/2025 | ANSON MAGLASANG |
| CofO Issued-Status Void | 1/7/2025 | ANSON MAGLASANG |
| Permit Finaled-Status Void | 1/7/2025 | ANSON MAGLASANG |
| Permit Finaled | 1/7/2025 | ANSON MAGLASANG |
| CofO Corrected | 1/7/2025 | ANSON MAGLASANG |
| Permit Finaled | 1/7/2025 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 3/16/2024 | CELINA MORENO |
| Permit | Cleared | 3/16/2024 | CELINA MORENO |
| Low Impact Development (LID) | Cleared | 3/19/2024 | LUIS CRUZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/21/2024 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 3/21/2024 | CELINA MORENO |
| Sewer availability | Cleared | 3/21/2024 | CELINA MORENO |
| Hydrant and Access approval | Cleared | 4/19/2024 | GILBERT URREA |
| Trees in Parkway | Cleared | 4/30/2024 | ADALBERTO VERA |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: NA81695 | , |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/5/2024 | Approved | ANSON MAGLASANG |
| Underground Mechanical | 7/16/2024 | Partial Approval | BEN MOLSTAD |
| Wood Frame | 7/16/2024 | Partial Approval | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 7/17/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Insulation | 7/17/2024 | Partial Approval | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 7/18/2024 | Partial Approval | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 7/24/2024 | Partial Approval | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 8/26/2024 | Approved | BARRY HACHE |
| Special/Order Compliance | 8/26/2024 | Partial Approval | BEN MOLSTAD |
| HVAC-Rough | 9/10/2024 | Corrections Issued | BARRY HACHE |
| ELECTRICAL-Rough | 9/11/2024 | Corrections Issued | BARRY HACHE |
| BUILDING-Rough-Frame | 9/12/2024 | Corrections Issued | BARRY HACHE |
| Green Building Rough | 9/12/2024 | Approved | BARRY HACHE |
| Verify Sprinkler Sign Off | 9/12/2024 | Approved | BARRY HACHE |
| Insulation | 9/16/2024 | Corrections Issued | BARRY HACHE |
| Drywall Nailing | 9/20/2024 | Approved | BARRY HACHE |
| Interior/Exterior Lathing | 9/20/2024 | Not Ready for Inspection | BARRY HACHE |
| Interior/Exterior Lathing | 9/24/2024 | Approved | BARRY HACHE |
| ELECTRICAL-Final | 10/24/2024 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Final | 11/5/2024 | Conditional Approval | ANTHONY EGSON |
| HVAC-Final | 11/21/2024 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 11/21/2024 | Not Ready for Inspection | ANTHONY EGSON |
| BUILDING-Rough-Frame | 11/25/2024 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 11/25/2024 | Approved | ANTHONY EGSON |
| Final | 11/25/2024 | OK to Issue CofO | ANTHONY EGSON |
| Green Building Final | 11/25/2024 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 11/25/2024 | Approved | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 11/25/2024 | SGSOV Not Required | ANTHONY EGSON |
| Service/Power Release | 11/25/2024 | Approved | ANTHONY EGSON |
| Smoke Detectors | 11/25/2024 | Approved | ANTHONY EGSON |