2223 W CLIFFORD ST 105 90026
Certificate Information: 2223 W CLIFFORD ST 105 90026
- Application / Permit
- 24010-10000-00463
- Plan Check / Job No.
- B23LA21305
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: (N) 1-STORY ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33 (c)-(d), (g)
- Permit Issued
- Issued on 2/26/2024
- Issuing Office
- Current Status
- CofO Issued on 7/22/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/11/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/21/2023 | DANIEL YIP |
| Corrections Issued | 11/28/2023 | DANIEL YIP |
| Quality Review Completed | 11/30/2023 | GARO TELMI |
| Applicant returned to address corrections | 2/7/2024 | DANIEL YIP |
| Plan Check Approved | 2/23/2024 | DANIEL YIP |
| No Progress | 2/26/2024 | DANIEL YIP |
| Plan Check Approved | 2/26/2024 | DANIEL YIP |
| Issued | 2/26/2024 | APPLICANT |
| CofO in Progress | 6/27/2024 | HAMIK HARTOUNIAN |
| CofO Issued | 7/22/2024 | DEROLD HAUFF |
| Permit Finaled | 7/22/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 2/8/2024 | ALEXANDER HELFER |
| Roof/Waste drainage to street | Cleared | 2/9/2024 | DAVID LOPEZ |
| Address approval | Cleared | 2/11/2024 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/11/2024 | ADRIAN SANCHEZ |
| GPI Written Notices | Cleared | 2/12/2024 | DANIEL YIP |
| Sewer availability | Cleared | 2/12/2024 | DAVID LOPEZ |
Contact Information
| Architect | Maly,, Farzin; Lic. No.: C33731 | 7136 HASKELL AVENUE # 320 VAN NUYS, CA 91406 |
| Contractor | Owner-Builder | , |
| Engineer | Sayah,, Daniel H; Lic. No.: C67905 | 15233 VENTURA BLVD STE 1130 SHERMAN OAKS, CA 91403 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/28/2024 | Partial Inspection | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 3/5/2024 | Partial Approval | THOMAS LOGRASSO |
| PLUMBING-Rough | 3/5/2024 | Partial Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 3/8/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 3/13/2024 | Approved | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 3/18/2024 | Corrections Issued | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 3/19/2024 | Partial Approval | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| HVAC-Rough | 4/1/2024 | Corrections Issued | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 4/2/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| PLUMBING-Rough | 4/4/2024 | Approved | THOMAS LOGRASSO |
| Underground Mechanical | 4/4/2024 | Corrections Issued | THOMAS LOGRASSO |
| HVAC-Rough | 4/10/2024 | Approved | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 4/15/2024 | Corrections Issued | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 4/15/2024 | Corrections Issued | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 4/17/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 4/17/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Verify Sprinkler Sign Off | 4/17/2024 | Approved | THOMAS LOGRASSO |
| Shower Pan | 4/19/2024 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 4/22/2024 | Approved | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 4/22/2024 | Approved | THOMAS LOGRASSO |
| Insulation | 4/22/2024 | Corrections Issued | THOMAS LOGRASSO |
| Insulation | 4/25/2024 | Conditional Approval | JOSEPH MCGARRY |
| Green Building Rough | 5/3/2024 | Approved | THOMAS LOGRASSO |
| Insulation | 5/3/2024 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 5/3/2024 | Approved | THOMAS LOGRASSO |
| Drywall Nailing | 5/6/2024 | Approved | BRENDAN MORELLI |
| Gas Test | 6/10/2024 | Approved | BRENDAN MORELLI |
| PLUMBING-Final | 6/10/2024 | Approved | BRENDAN MORELLI |
| ELECTRICAL-Final | 6/18/2024 | Approved | HAMIK HARTOUNIAN |
| Service/Power Release | 6/18/2024 | Approved | HAMIK HARTOUNIAN |
| Final | 6/20/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Final | 6/20/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| HVAC-Final | 6/20/2024 | Approved | HAMIK HARTOUNIAN |
| MERV13>=Final | 6/20/2024 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 6/20/2024 | SGSOV Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 6/20/2024 | Approved | HAMIK HARTOUNIAN |
| Final | 6/26/2024 | OK to Issue CofO | HAMIK HARTOUNIAN |
| Green Building Final | 6/26/2024 | Approved | HAMIK HARTOUNIAN |