9410 S WILMINGTON AVE 90002
Certificate Information: 9410 S WILMINGTON AVE 90002
- Application / Permit
- 24010-10000-00452
- Plan Check / Job No.
- B24LA02108
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1 OF 2 (N) 2-STORY SINGLE FAMILY DWELLING. NFPA 13D FIRE SPRINKLERS THROUGH OUT. NO PARKING REQUIRED PER AB2097.
- Permit Issued
- Issued on 9/24/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/18/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/6/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/8/2024 | ADRIANA LOPEZ |
| Corrections Issued | 3/5/2024 | ADRIANA LOPEZ |
| Quality Review Completed | 3/13/2024 | KEN GILL |
| Building Plans Picked Up | 3/14/2024 | APPLICANT |
| Applicant returned to address corrections | 8/16/2024 | ADRIANA LOPEZ |
| Applicant returned to address corrections | 9/19/2024 | ADRIANA LOPEZ |
| Plan Check Approved | 9/19/2024 | ADRIANA LOPEZ |
| Issued | 9/24/2024 | APPLICANT |
| CofO in Progress | 2/11/2026 | ARTHUR NEGRETE |
| Permit Finaled | 3/18/2026 | ANSON MAGLASANG |
| CofO Issued | 3/18/2026 | ANSON MAGLASANG |
| Permit Finaled | 3/18/2026 | ANSON MAGLASANG |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 5/17/2024 | MATTHEW CRAIG |
| Address approval | Cleared | 5/31/2024 | DAVID LOPEZ |
| Low Impact Development (LID) | Cleared | 6/18/2024 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 6/20/2024 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 7/2/2024 | DAVID LOPEZ |
| Sewer availability | Cleared | 7/2/2024 | DAVID LOPEZ |
Contact Information
| Contractor | Ebenezer Construction; Lic. No.: 657529-B | 9214 MANZANAR AVE DOWNEY, CA 90240 |
| Engineer | Sandoval,, Martin; Lic. No.: C56905 | 12761 DAIRY ST EASTVALE, CA 92880 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/9/2024 | Corrections Issued | BARRY HACHE |
| Underground Mechanical | 10/9/2024 | Not Ready for Inspection | BARRY HACHE |
| Excavation/Setback/Form/Re-Bar | 10/23/2024 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 10/23/2024 | Partial Approval | ANTHONY EGSON |
| Sewer | 10/23/2024 | Approved | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 11/7/2024 | Corrections Issued | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 11/12/2024 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/6/2024 | Corrections Issued | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/12/2024 | Partial Approval | ANTHONY EGSON |
| Deputy Wood Construction | 1/2/2025 | Conditional Approval | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/21/2025 | Partial Approval | ANTHONY EGSON |
| Wood Frame | 3/11/2025 | Partial Approval | ANTHONY EGSON |
| ELECTRICAL-Rough | 4/15/2025 | Corrections Issued | ANTHONY EGSON |
| HVAC-Rough | 4/15/2025 | Not Ready for Inspection | ANTHONY EGSON |
| PLUMBING-Rough | 4/15/2025 | Corrections Issued | ANTHONY EGSON |
| BUILDING-Rough-Frame | 5/12/2025 | Corrections Issued | ANTHONY EGSON |
| Green Building Rough | 5/12/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Rough-Elec/Plmb/HVAC | 5/12/2025 | Partial Approval | ANTHONY EGSON |
| Verify Sprinkler Sign Off | 5/12/2025 | Not Ready for Inspection | ANTHONY EGSON |
| BUILDING-Rough-Frame | 5/23/2025 | Corrections Issued | ANTHONY EGSON |
| Green Building Rough | 5/23/2025 | Corrections Issued | ANTHONY EGSON |
| Verify Sprinkler Sign Off | 5/23/2025 | Not Ready for Inspection | ANTHONY EGSON |
| BUILDING-Rough-Frame | 6/2/2025 | Approved | ANTHONY EGSON |
| Green Building Rough | 6/2/2025 | Approved | ANTHONY EGSON |
| Verify Sprinkler Sign Off | 6/2/2025 | Approved | ANTHONY EGSON |
| Insulation | 6/12/2025 | Approved | ANTHONY EGSON |
| Drywall Nailing | 6/26/2025 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 6/26/2025 | Approved | ANTHONY EGSON |
| Sewer | 9/15/2025 | Corrections Issued | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 12/23/2025 | SGSOV Not Ready | ARTHUR NEGRETE |
| SGSOV-Seismic Gas S/O Valve | 12/30/2025 | SGSOV Not Ready | ARTHUR NEGRETE |
| ELECTRICAL-Final | 2/10/2026 | Approved | ARTHUR NEGRETE |
| Final | 2/10/2026 | OK to Issue CofO | ARTHUR NEGRETE |
| Footing/Foundation/Slab | 2/10/2026 | Approved | ARTHUR NEGRETE |
| Green Building Final | 2/10/2026 | Approved | ARTHUR NEGRETE |
| HVAC-Final | 2/10/2026 | Approved | ARTHUR NEGRETE |
| PLUMBING-Final | 2/10/2026 | Approved | ARTHUR NEGRETE |
| SGSOV-Seismic Gas S/O Valve | 2/10/2026 | SGSOV Not Required | ARTHUR NEGRETE |
| Service/Power Release | 2/10/2026 | Approved | ARTHUR NEGRETE |
| Smoke Detectors | 2/10/2026 | Approved | ARTHUR NEGRETE |