2659 S BUDLONG AVE 1-60 90007

Certificate Information: 2659 S BUDLONG AVE 1-60 90007

Application / Permit
24010-10000-00435
Plan Check / Job No.
B24LA02019
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 6 STORY WITH ROOF DECK 60 UNITS (48 LI + 12 MI) AFFORDABLE HOUSING APARTMENT TO INCLUDE 5 STORY TYPE IIIA APARTMENT OVER 1 STORY TYPE IA PARKING, USING 12.22.A.25 INCENTIVES
Permit Issued
Issued on 3/31/2026
Issuing Office
Current Status
Issued on 3/31/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/5/2024 APPLICANT
Assigned to Plan Check Engineer 2/8/2024 STARR CHEN
Assigned to Zoning Architect 2/8/2024 KAITA SAITO
Corrections Issued 2/12/2024 STARR CHEN
Quality Review Completed 2/13/2024 EUGENE BARBEAU
Applicant returned to address corrections 9/23/2024 MANUEL MONTUFAR
Plan Check Approved 3/17/2026 MANUEL MONTUFAR
Issued 3/31/2026 APPLICANT

Permit Application Clearance Information

Address approval Cleared 8/16/2024 TREVOR QUAN
Construction near power lines Cleared 9/30/2024 ENRIQUE ACOSTA
Highway dedication Cleared 10/2/2024 CHRISTINA BRACO
Permit Cleared 10/8/2024 CHRISTINA BRACO
Eng Process Fee Ord 176,300 Cleared 10/11/2024 CHRISTINA BRACO
Green Code Cleared 10/23/2024 STARR CHEN
Sewer availability Cleared 10/23/2024 CELINA MORENO
Low Impact Development (LID) Cleared 10/25/2024 MARTIN FRAGOSO
Encroachment in public way Cleared 11/5/2024 MARK REYES
Trees in Parkway Cleared 11/13/2024 ADALBERTO VERA
Roof/Waste drainage to street Cleared 12/5/2024 CHRISTINA BRACO
Hydrant and Access approval Cleared 1/16/2025 LAVEON RIDER
HPOZ Cleared 1/28/2025 DANIEL MATA
ZI Cleared 1/28/2025 DANIEL MATA
CPC Cleared 2/19/2025 ROSALINDA MEZA
Miscellaneous Cleared 2/19/2025 ROSALINDA MEZA
Miscellaneous Cleared 2/19/2025 ROSALINDA MEZA
Fire Marshal Fire Life Safety Cleared 3/4/2025 RONILO MULAWIN
Building over 36-ft Cleared 3/10/2025 CALOSHA APPROVED
DAS Clearance Cleared 4/10/2025 STARR CHEN
Density Bonus Cleared 6/18/2025 LOUIE MILLER
SB8 RUD Cleared 6/18/2025 LOUIE MILLER
Frnt yard landscape/Water mgmt Cleared 7/1/2025 ROSALINDA MEZA
Miscellaneous Cleared 7/1/2025 ROSALINDA MEZA
Miscellaneous Cleared 7/1/2025 ROSALINDA MEZA
Miscellaneous Cleared 7/1/2025 ROSALINDA MEZA
Miscellaneous Cleared 7/1/2025 ROSALINDA MEZA
Miscellaneous Cleared 7/1/2025 ROSALINDA MEZA
Opn space landscape/Water mgmt Cleared 7/1/2025 ROSALINDA MEZA
ZI Cleared 7/1/2025 ROSALINDA MEZA
Public Housing Cleared 3/4/2026 GORDON ZUBER
Zoning Plan Check Cleared 3/5/2026 KAITA SAITO

Contact Information

Architect Park,, Jay H.; Lic. No.: C36800 3850 WILSHIRE BLVD #308      LOS ANGELES, CA 90010
Contractor Owner-Builder       ,
Engineer Hwang,, Junho; Lic. No.: S5592 2450 W MAIN ST      ALHAMBRA, CA 91801
Engineer Nazemi,, Hassan Steve; Lic. No.: C44100 275 CENTENNIAL WAY 205      TUSTIN, CA 92780
Engineer Smith,, Melvin Bruce; Lic. No.: GE2673 2165 N MARVEL AVE      SIMI VALLEY, CA 93065
Geologist Kaligi,, Adam Azad; Lic. No.: GEO9287 19197 GOLDEN VALLEY RD #709      SANTA CLARITA, CA 91387
Landscape Architect Lewis,, Paul Adam; Lic. No.: LA3620 13351-D RIVERSIDE DR #445      SHERMAN OAKS, CA 91423

Inspector Information

ALFREDO LOPEZ, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI
JAMES POWERS, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 6/1/2026 Partial Approval JAMES POWERS
Footing/Foundation/Slab 6/1/2026 Partial Approval JAMES POWERS
METHANE-Barrier 6/1/2026 Not Ready for Inspection JAMES POWERS
METHANE-Subgrade 6/1/2026 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 6/4/2026 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/18/2026 Partial Approval JAMES POWERS
Green Building Rough 6/18/2026 Not Ready for Inspection JAMES POWERS
METHANE-Barrier 6/18/2026 Not Ready for Inspection JAMES POWERS
METHANE-Rough 6/18/2026 Not Ready for Inspection JAMES POWERS
METHANE-Subgrade 6/18/2026 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 6/18/2026 Partial Approval JAMES POWERS
Reinforced Masonry Frame 6/18/2026 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 6/18/2026 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 7/2/2026 Partial Approval JAMES POWERS
Green Building Rough 7/2/2026 Not Ready for Inspection JAMES POWERS
METHANE-Rough 7/2/2026 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 7/2/2026 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 7/2/2026 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 7/8/2026 Partial Approval JAMES POWERS
Footing/Foundation/Slab 7/15/2026 Partial Approval JAMES POWERS
Green Building Rough 7/15/2026 Not Ready for Inspection JAMES POWERS
METHANE-Barrier 7/15/2026 Not Ready for Inspection JAMES POWERS
METHANE-Rough 7/15/2026 Not Ready for Inspection JAMES POWERS
METHANE-Subgrade 7/15/2026 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 7/15/2026 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 7/15/2026 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 7/23/2026 Partial Approval JAMES POWERS