2659 S BUDLONG AVE 1-60 90007
Certificate Information: 2659 S BUDLONG AVE 1-60 90007
- Application / Permit
- 24010-10000-00435
- Plan Check / Job No.
- B24LA02019
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- NEW 6 STORY WITH ROOF DECK 60 UNITS (48 LI + 12 MI) AFFORDABLE HOUSING APARTMENT TO INCLUDE 5 STORY TYPE IIIA APARTMENT OVER 1 STORY TYPE IA PARKING, USING 12.22.A.25 INCENTIVES
- Permit Issued
- Issued on 3/31/2026
- Issuing Office
- Current Status
- Issued on 3/31/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/5/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/8/2024 | STARR CHEN |
| Assigned to Zoning Architect | 2/8/2024 | KAITA SAITO |
| Corrections Issued | 2/12/2024 | STARR CHEN |
| Quality Review Completed | 2/13/2024 | EUGENE BARBEAU |
| Applicant returned to address corrections | 9/23/2024 | MANUEL MONTUFAR |
| Plan Check Approved | 3/17/2026 | MANUEL MONTUFAR |
| Issued | 3/31/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 8/16/2024 | TREVOR QUAN |
| Construction near power lines | Cleared | 9/30/2024 | ENRIQUE ACOSTA |
| Highway dedication | Cleared | 10/2/2024 | CHRISTINA BRACO |
| Permit | Cleared | 10/8/2024 | CHRISTINA BRACO |
| Eng Process Fee Ord 176,300 | Cleared | 10/11/2024 | CHRISTINA BRACO |
| Green Code | Cleared | 10/23/2024 | STARR CHEN |
| Sewer availability | Cleared | 10/23/2024 | CELINA MORENO |
| Low Impact Development (LID) | Cleared | 10/25/2024 | MARTIN FRAGOSO |
| Encroachment in public way | Cleared | 11/5/2024 | MARK REYES |
| Trees in Parkway | Cleared | 11/13/2024 | ADALBERTO VERA |
| Roof/Waste drainage to street | Cleared | 12/5/2024 | CHRISTINA BRACO |
| Hydrant and Access approval | Cleared | 1/16/2025 | LAVEON RIDER |
| HPOZ | Cleared | 1/28/2025 | DANIEL MATA |
| ZI | Cleared | 1/28/2025 | DANIEL MATA |
| CPC | Cleared | 2/19/2025 | ROSALINDA MEZA |
| Miscellaneous | Cleared | 2/19/2025 | ROSALINDA MEZA |
| Miscellaneous | Cleared | 2/19/2025 | ROSALINDA MEZA |
| Fire Marshal Fire Life Safety | Cleared | 3/4/2025 | RONILO MULAWIN |
| Building over 36-ft | Cleared | 3/10/2025 | CALOSHA APPROVED |
| DAS Clearance | Cleared | 4/10/2025 | STARR CHEN |
| Density Bonus | Cleared | 6/18/2025 | LOUIE MILLER |
| SB8 RUD | Cleared | 6/18/2025 | LOUIE MILLER |
| Frnt yard landscape/Water mgmt | Cleared | 7/1/2025 | ROSALINDA MEZA |
| Miscellaneous | Cleared | 7/1/2025 | ROSALINDA MEZA |
| Miscellaneous | Cleared | 7/1/2025 | ROSALINDA MEZA |
| Miscellaneous | Cleared | 7/1/2025 | ROSALINDA MEZA |
| Miscellaneous | Cleared | 7/1/2025 | ROSALINDA MEZA |
| Miscellaneous | Cleared | 7/1/2025 | ROSALINDA MEZA |
| Opn space landscape/Water mgmt | Cleared | 7/1/2025 | ROSALINDA MEZA |
| ZI | Cleared | 7/1/2025 | ROSALINDA MEZA |
| Public Housing | Cleared | 3/4/2026 | GORDON ZUBER |
| Zoning Plan Check | Cleared | 3/5/2026 | KAITA SAITO |
Contact Information
| Architect | Park,, Jay H.; Lic. No.: C36800 | 3850 WILSHIRE BLVD #308 LOS ANGELES, CA 90010 |
| Contractor | Owner-Builder | , |
| Engineer | Hwang,, Junho; Lic. No.: S5592 | 2450 W MAIN ST ALHAMBRA, CA 91801 |
| Engineer | Nazemi,, Hassan Steve; Lic. No.: C44100 | 275 CENTENNIAL WAY 205 TUSTIN, CA 92780 |
| Engineer | Smith,, Melvin Bruce; Lic. No.: GE2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
| Geologist | Kaligi,, Adam Azad; Lic. No.: GEO9287 | 19197 GOLDEN VALLEY RD #709 SANTA CLARITA, CA 91387 |
| Landscape Architect | Lewis,, Paul Adam; Lic. No.: LA3620 | 13351-D RIVERSIDE DR #445 SHERMAN OAKS, CA 91423 |
Inspector Information
| ALFREDO LOPEZ, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
| JAMES POWERS, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 6/1/2026 | Partial Approval | JAMES POWERS |
| Footing/Foundation/Slab | 6/1/2026 | Partial Approval | JAMES POWERS |
| METHANE-Barrier | 6/1/2026 | Not Ready for Inspection | JAMES POWERS |
| METHANE-Subgrade | 6/1/2026 | Not Ready for Inspection | JAMES POWERS |
| Deputy Reinf. Concrete | 6/4/2026 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 6/18/2026 | Partial Approval | JAMES POWERS |
| Green Building Rough | 6/18/2026 | Not Ready for Inspection | JAMES POWERS |
| METHANE-Barrier | 6/18/2026 | Not Ready for Inspection | JAMES POWERS |
| METHANE-Rough | 6/18/2026 | Not Ready for Inspection | JAMES POWERS |
| METHANE-Subgrade | 6/18/2026 | Not Ready for Inspection | JAMES POWERS |
| Reinforced Concrete Frame | 6/18/2026 | Partial Approval | JAMES POWERS |
| Reinforced Masonry Frame | 6/18/2026 | Not Ready for Inspection | JAMES POWERS |
| Verify Sprinkler Sign Off | 6/18/2026 | Not Ready for Inspection | JAMES POWERS |
| Deputy Reinf. Concrete | 7/2/2026 | Partial Approval | JAMES POWERS |
| Green Building Rough | 7/2/2026 | Not Ready for Inspection | JAMES POWERS |
| METHANE-Rough | 7/2/2026 | Not Ready for Inspection | JAMES POWERS |
| Reinforced Concrete Frame | 7/2/2026 | Partial Approval | JAMES POWERS |
| Verify Sprinkler Sign Off | 7/2/2026 | Not Ready for Inspection | JAMES POWERS |
| Deputy Reinf. Concrete | 7/8/2026 | Partial Approval | JAMES POWERS |
| Footing/Foundation/Slab | 7/15/2026 | Partial Approval | JAMES POWERS |
| Green Building Rough | 7/15/2026 | Not Ready for Inspection | JAMES POWERS |
| METHANE-Barrier | 7/15/2026 | Not Ready for Inspection | JAMES POWERS |
| METHANE-Rough | 7/15/2026 | Not Ready for Inspection | JAMES POWERS |
| METHANE-Subgrade | 7/15/2026 | Not Ready for Inspection | JAMES POWERS |
| Reinforced Concrete Frame | 7/15/2026 | Not Ready for Inspection | JAMES POWERS |
| Verify Sprinkler Sign Off | 7/15/2026 | Not Ready for Inspection | JAMES POWERS |
| Deputy Reinf. Concrete | 7/23/2026 | Partial Approval | JAMES POWERS |