2143 W 85TH ST 90047
Certificate Information: 2143 W 85TH ST 90047
- Application / Permit
- 24010-10000-00393
- Plan Check / Job No.
- B24LA01789
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2-STORY ADU WITH ATTACHED GARAGE AND STORAGE PER ORDINANCE
- Permit Issued
- Issued on 6/6/2024
- Issuing Office
- South Los Angeles
- Current Status
- Issued on 6/6/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/31/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/15/2024 | WEIJIAN HUANG |
| Corrections Issued | 2/22/2024 | WEIJIAN HUANG |
| Building Plans Picked Up | 3/5/2024 | APPLICANT |
| Quality Review Completed | 3/6/2024 | DANIEL CHAN |
| Applicant returned to address corrections | 4/3/2024 | WEIJIAN HUANG |
| Plan Check Approved | 4/9/2024 | WEIJIAN HUANG |
| Issued | 6/6/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 3/12/2024 | CHRISTINA BRACO |
| Eng Process Fee Ord 176,300 | Cleared | 3/20/2024 | CHRISTINA BRACO |
| Sewer availability | Cleared | 3/20/2024 | CHRISTINA BRACO |
| ZA Case | Cleared | 3/21/2024 | GEORGIA SMITH |
| Construction near power lines | Cleared | 3/22/2024 | DANIEL ROCHA |
| Low Impact Development (LID) | Cleared | 4/5/2024 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 4/8/2024 | WALLIE JONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Bustillos, Portillo, Alejandro; Lic. No.: C87257 | 4749 W 169TH STREET LAWNDALE, CA 90260 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 6/28/2024 | Approved | JOSE MACIAS |
| Footing/Foundation/Slab | 7/10/2024 | Approved | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 9/4/2024 | Corrections Issued | AMIR NAZARIAN |
| ELECTRICAL-Rough | 10/9/2024 | Corrections Issued | AMIR NAZARIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/9/2024 | Corrections Issued | AMIR NAZARIAN |
| HVAC-Rough | 10/9/2024 | Approved | AMIR NAZARIAN |
| PLUMBING-Rough | 10/9/2024 | Corrections Issued | AMIR NAZARIAN |
| Deputy Wood Construction | 10/10/2024 | No Access for Inspection | AMIR NAZARIAN |
| ELECTRICAL-Rough | 10/22/2024 | Conditional Approval | AMIR NAZARIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/22/2024 | Approved | AMIR NAZARIAN |
| PLUMBING-Rough | 10/22/2024 | Approved | AMIR NAZARIAN |
| Pre-Inspection | 10/22/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Interior/Exterior Lathing | 10/29/2024 | Partial Approval | JOSH MEISTER |
| Insulation | 11/1/2024 | Corrections Issued | ALEX COLIN |
| BUILDING-Rough-Frame | 11/12/2024 | Approved | AMIR NAZARIAN |
| Drywall Nailing | 11/12/2024 | Approved | AMIR NAZARIAN |
| Green Building Rough | 11/12/2024 | Approved | AMIR NAZARIAN |
| Verify Sprinkler Sign Off | 11/12/2024 | Approved | AMIR NAZARIAN |
| Interior/Exterior Lathing | 12/5/2024 | Approved | ANTHONY RAMOS |
| Final | 3/10/2025 | Corrections Issued | JOHN QUINTANILLA |
| Green Building Final | 3/10/2025 | Approved | JOHN QUINTANILLA |
| SGSOV-Seismic Gas S/O Valve | 3/10/2025 | SGSOV No Gas | JOHN QUINTANILLA |
| Service/Power Release | 3/10/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| Smoke Detectors | 3/10/2025 | Approved | JOHN QUINTANILLA |
| Final | 3/13/2025 | Not Ready for Inspection | JOSE MACIAS |
| Service/Power Release | 3/13/2025 | Not Ready for Inspection | JOSE MACIAS |
| Final | 4/7/2025 | Partial Approval | WAYNE REGESTER |
| Service/Power Release | 4/7/2025 | Approved | WAYNE REGESTER |