3310 E GARNET ST 90023
Certificate Information: 3310 E GARNET ST 90023
- Application / Permit
- 24010-10000-00386
- Plan Check / Job No.
- B24LA01756
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Two story ground floor addition to (E) Garage resolting to Garage and Rec room on the first floor and ADU per LAMC 12.22 A.33 (c)-(d) on the secound floor
- Permit Issued
- Issued on 4/8/2025
- Issuing Office
- Current Status
- Issued on 4/8/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/5/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/22/2024 | GEORGE JOLAKIAN |
| Corrections Issued | 2/29/2024 | GEORGE JOLAKIAN |
| Quality Review Completed | 3/12/2024 | RODOLFO ARIAS |
| Plan Check Approved | 1/23/2025 | GEORGE JOLAKIAN |
| Issued | 4/8/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 3/19/2024 | DAVID LOPEZ |
| Construction near power lines | Cleared | 6/25/2024 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 7/1/2024 | DAVID LOPEZ |
| Sewer availability | Cleared | 7/1/2024 | DAVID LOPEZ |
| Grading Pre-Inspection | Cleared | 7/11/2024 | RUSSELL BONVOULOIR |
| Low Impact Development (LID) | Cleared | 9/19/2024 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 9/30/2024 | DAVID LOPEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Basma,, Ali J; Lic. No.: C53080 | 6047 TAMPA AVE SUITE 304 TARZANA, CA 91356 |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/9/2025 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Rough | 7/22/2025 | Corrections Issued | FREDDIE RIVERA |
| PLUMBING-Rough | 7/22/2025 | Partial Approval | FREDDIE RIVERA |
| Special/Order Compliance | 7/22/2025 | Partial Inspection | OSVALDO PARAMO |
| Footing/Foundation/Slab | 9/5/2025 | Approved | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 2/10/2026 | Partial Approval | JUSTIN HAWLEY |
| Underground Mechanical | 2/10/2026 | Partial Approval | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 3/20/2026 | Partial Approval | FREDDIE RIVERA |
| Deputy Drilled-In Anchors | 4/10/2026 | Conditional Approval | FREDDIE RIVERA |
| Deputy Wood Construction | 4/10/2026 | Conditional Approval | FREDDIE RIVERA |
| Gas Test | 5/7/2026 | Approved | JOSH MEISTER |
| Rough-Elec/Plmb/HVAC | 5/7/2026 | Approved | JOSH MEISTER |
| BUILDING-Rough-Frame | 5/20/2026 | Approved | FREDDIE RIVERA |
| Green Building Rough | 5/20/2026 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 5/20/2026 | Partial Approval | FREDDIE RIVERA |
| MERV13>=Rough | 5/20/2026 | Approved | FREDDIE RIVERA |
| Insulation | 5/26/2026 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 5/29/2026 | Approved | JUSTIN HAWLEY |