817-817 1/2 W 76TH ST 90044

Certificate Information: 817-817 1/2 W 76TH ST 90044

Application / Permit
24010-10000-00284
Plan Check / Job No.
B24LA01321
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
E-PLAN. NEW 2-STORY DUPLEX W/ ATTACHED 2-CAR GARAGE
Permit Issued
Issued on 7/11/2024
Issuing Office
Current Status
CofO Issued on 12/10/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/25/2024 APPLICANT
Assigned to Plan Check Engineer 2/22/2024 ARSALAN SHABESTARI
Corrections Issued 2/27/2024 ARSALAN SHABESTARI
Quality Review Completed 3/15/2024 YOUNG KIM
Plan Check Approved 7/2/2024 ARSALAN SHABESTARI
Issued 7/11/2024 APPLICANT
CofO in Progress 12/9/2024 MICHAEL LEWIS
Permit Finaled 12/10/2024 DEROLD HAUFF
CofO Issued 12/10/2024 DEROLD HAUFF
Permit Finaled 12/10/2024 DEROLD HAUFF

Permit Application Clearance Information

Low Impact Development (LID) Cleared 3/27/2024 MELINEH AGHAKHABIAN
ZI Cleared 4/2/2024 BRENNEN OBETO
Address approval Cleared 4/3/2024 DAVID VO
Roof/Waste drainage to street Cleared 4/3/2024 DAVID VO
Eng Process Fee Ord 176,300 Cleared 4/8/2024 JUSTIN BICOL
Sewer availability Cleared 4/8/2024 JUSTIN BICOL
Hydrant and Access approval Cleared 5/2/2024 MATTHEW CRAIG
Highway dedication Cleared 5/17/2024 CELINA MORENO

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B       ,
Engineer Madero,, Fidencio; Lic. No.: NA81695       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/2/2024 Approved MICHAEL LEWIS
Footing/Foundation/Slab 8/2/2024 Approved MICHAEL LEWIS
PLUMBING-Rough 8/15/2024 Partial Approval MICHAEL LEWIS
Wood Frame 8/15/2024 Partial Approval MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 8/16/2024 Partial Approval MICHAEL LEWIS
Insulation 8/16/2024 Partial Approval MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 8/23/2024 Partial Approval MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 9/13/2024 Approved MICHAEL LEWIS
HVAC-Rough 10/4/2024 Approved LUIS CASTRO
PLUMBING-Rough 10/4/2024 Approved LUIS CASTRO
BUILDING-Rough-Frame 10/7/2024 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 10/7/2024 Approved ALEJANDRO DE ARTOLA
Green Building Rough 10/7/2024 Approved ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 10/7/2024 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 10/8/2024 Approved ALEJANDRO DE ARTOLA
Insulation 10/8/2024 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 10/21/2024 Approved ALEX COLIN
Interior/Exterior Lathing 10/21/2024 Approved ALEX COLIN
ELECTRICAL-Final 11/25/2024 Partial Approval MICHAEL LEWIS
Service/Power Release 11/25/2024 Approved MICHAEL LEWIS
HVAC-Final 12/5/2024 Approved MICHAEL LEWIS
PLUMBING-Final 12/5/2024 Approved MICHAEL LEWIS
ELECTRICAL-Final 12/6/2024 Approved MICHAEL LEWIS
Final 12/6/2024 OK to Issue CofO MICHAEL LEWIS
Green Building Final 12/6/2024 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 12/6/2024 SGSOV Not Required MICHAEL LEWIS
Smoke Detectors 12/6/2024 Approved MICHAEL LEWIS