444 1/2 W 84TH PL 90003
Certificate Information: 444 1/2 W 84TH PL 90003
- Application / Permit
- 24010-10000-00258
- Plan Check / Job No.
- B24LA01213
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New detached ADU per GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c),(d), and (g).
- Permit Issued
- Issued on 3/19/2024
- Issuing Office
- Metro
- Current Status
- Issued on 3/19/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/23/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/25/2024 | HUAN LE |
| Corrections Issued | 2/1/2024 | HUAN LE |
| Building Plans Picked Up | 2/2/2024 | APPLICANT |
| Applicant returned to address corrections | 3/8/2024 | DANIEL SMILEY |
| Applicant returned to address corrections | 3/12/2024 | KELVIN CHUONG |
| Plan Check Approved | 3/19/2024 | SHANGQIN XIE |
| Issued | 3/19/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 2/9/2024 | ANTHONY TRAN |
| Roof/Waste drainage to street | Cleared | 2/9/2024 | ANTHONY TRAN |
| Eng Process Fee Ord 176,300 | Cleared | 2/27/2024 | JEANIE LAM |
| Sewer availability | Cleared | 2/27/2024 | JEANIE LAM |
| Community Plan Implem. Overlay | Cleared | 3/1/2024 | CELINA MORENO |
| Community Plan Implem. Overlay | Cleared | 3/1/2024 | EDGAR PASCUA |
| Community Plan Implem. Overlay | Cleared | 3/1/2024 | MANERI ROMAN |
| Community Plan Implem. Overlay | Cleared | 3/7/2024 | DYNL MIRANDA |
| Miscellaneous | Cleared | 3/8/2024 | NOAH MCCOY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 5/1/2024 | Approved | MICHAEL LEWIS |
| Excavation/Setback/Form/Re-Bar | 5/7/2024 | Approved | MICHAEL LEWIS |
| Footing/Foundation/Slab | 5/7/2024 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Rough | 7/2/2024 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 7/2/2024 | Corrections Issued | MICHAEL LEWIS |
| HVAC-Rough | 7/2/2024 | Approved | MICHAEL LEWIS |
| PLUMBING-Rough | 7/2/2024 | Corrections Issued | MICHAEL LEWIS |
| Insulation | 7/15/2024 | Corrections Issued | MICHAEL LEWIS |
| Interior/Exterior Lathing | 7/15/2024 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 7/17/2024 | Conditional Approval | MICHAEL LEWIS |
| Green Building Rough | 7/17/2024 | Approved | MICHAEL LEWIS |
| MERV13>=Rough | 7/17/2024 | Approved | MICHAEL LEWIS |
| Verify Sprinkler Sign Off | 7/17/2024 | Conditional Approval | MICHAEL LEWIS |
| Insulation | 7/19/2024 | Approved | MICHAEL LEWIS |
| Drywall Nailing | 7/25/2024 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 10/21/2024 | Partial Approval | MICHAEL LEWIS |
| Final | 10/21/2024 | Corrections Issued | MICHAEL LEWIS |
| Green Building Final | 10/21/2024 | Corrections Issued | MICHAEL LEWIS |
| MERV13>=Final | 10/21/2024 | Approved | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 10/21/2024 | SGSOV Not Required | MICHAEL LEWIS |
| Service/Power Release | 10/21/2024 | Corrections Issued | MICHAEL LEWIS |
| Smoke Detectors | 10/21/2024 | Approved | MICHAEL LEWIS |
| Verify Sprinkler Sign Off | 10/21/2024 | Partial Inspection | MICHAEL LEWIS |