3651 W 25TH ST 90018
Certificate Information: 3651 W 25TH ST 90018
- Application / Permit
- 24010-10000-00239
- Plan Check / Job No.
- B24LA01170
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 47'-3" X 20'-3" IRREGULAR SHAPED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d) WITH 5'-9" X 3'-0" ATTACHED PATIO COVER AT ENTRANCE
- Permit Issued
- Issued on 7/25/2024
- Issuing Office
- Current Status
- CofO Issued on 2/2/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/23/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/25/2024 | ALEC MOUSAKHANIAN |
| Corrections Issued | 1/26/2024 | ALEC MOUSAKHANIAN |
| Applicant returned to address corrections | 7/8/2024 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 7/21/2024 | ALEC MOUSAKHANIAN |
| Issued | 7/25/2024 | APPLICANT |
| CofO in Progress | 1/28/2025 | JUSTIN HAWLEY |
| Permit Finaled | 2/2/2025 | DEROLD HAUFF |
| Permit Finaled | 2/2/2025 | DEROLD HAUFF |
| CofO Issued | 2/2/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/1/2024 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/22/2024 | DAVID LOPEZ |
| Sewer availability | Cleared | 3/22/2024 | DAVID LOPEZ |
| Construction near power lines | Cleared | 5/30/2024 | RIDWAN HARDY |
| Low Impact Development (LID) | Cleared | 7/5/2024 | MITESH PATEL |
| HPOZ | Cleared | 7/8/2024 | DEBORAH MCGILL |
| Roof/Waste drainage to street | Cleared | 7/17/2024 | CELINA MORENO |
Contact Information
| Contractor | Julian Construction Inc; Lic. No.: 788526-B | , |
| Engineer | Truong,, Phong; Lic. No.: C70784 | 20439 E CRESTLINE DRIVE WALNUT, CA 91789 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/16/2024 | Approved | JUSTIN HAWLEY |
| Underground Mechanical | 8/28/2024 | Partial Approval | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 9/4/2024 | Partial Approval | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 9/20/2024 | Approved | WILLIAM SIERRA |
| PLUMBING-Rough | 9/27/2024 | Approved | JUSTIN HAWLEY |
| ELECTRICAL-Rough | 10/17/2024 | Corrections Issued | JUSTIN HAWLEY |
| Shower Pan | 10/17/2024 | Approved | JUSTIN HAWLEY |
| Underground Mechanical | 10/17/2024 | Partial Approval | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 10/21/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| ELECTRICAL-Rough | 10/21/2024 | Approved | JUSTIN HAWLEY |
| HVAC-Rough | 10/21/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 10/22/2024 | Partial Approval | JUSTIN HAWLEY |
| MERV13>=Rough | 10/22/2024 | Approved | JUSTIN HAWLEY |
| Insulation | 10/28/2024 | Approved | JOSE MACIAS |
| Interior/Exterior Lathing | 10/28/2024 | Approved | JOSE MACIAS |
| Drywall Nailing | 11/5/2024 | Approved | JOSH MEISTER |
| Interior/Exterior Lathing | 11/5/2024 | Approved | JOSH MEISTER |
| BUILDING-Rough-Frame | 1/22/2025 | Approved | JUSTIN HAWLEY |
| Final | 1/22/2025 | Corrections Issued | JUSTIN HAWLEY |
| Footing/Foundation/Slab | 1/22/2025 | Approved | JUSTIN HAWLEY |
| Green Building Final | 1/22/2025 | Approved | JUSTIN HAWLEY |
| MERV13>=Final | 1/22/2025 | Approved | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 1/22/2025 | SGSOV Not Required | JUSTIN HAWLEY |
| Service/Power Release | 1/22/2025 | Not Ready for Inspection | JUSTIN HAWLEY |
| Smoke Detectors | 1/22/2025 | Approved | JUSTIN HAWLEY |
| ELECTRICAL-Final | 1/28/2025 | Approved | JUSTIN HAWLEY |
| Final | 1/28/2025 | OK to Issue CofO | JUSTIN HAWLEY |
| HVAC-Final | 1/28/2025 | Approved | JUSTIN HAWLEY |
| PLUMBING-Final | 1/28/2025 | Approved | JUSTIN HAWLEY |
| Service/Power Release | 1/28/2025 | Approved | JUSTIN HAWLEY |