3418 S MOTOR AVE 90034
Certificate Information: 3418 S MOTOR AVE 90034
- Application / Permit
- 24010-10000-00188
- Plan Check / Job No.
- B24LA00864
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (5) Apartment
- Work Description
- NEW 100% PRIVATELY FUNDED 200-UNIT MIXED-USE (APARTMENT, RETAIL AND OFFICE) PROJECT WITHIN THE EXPOSITION TNP SPECIFIC PLAN, WITH AFFORDABLE HOUSING (22 EXTREMELY LOW UNITS) 1 OF 3
- Permit Issued
- No
- Current Status
- Quality Review Completed on 2/9/2024
Permit Application Status History
| Submitted | 1/17/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/25/2024 | JOE VO |
| Assigned to Zoning Architect | 1/25/2024 | NEVRIK NAVASARTIAN |
| Corrections Issued | 2/5/2024 | JOE VO |
| Quality Review Completed | 2/9/2024 | KEN GILL |
| Building Plans Picked Up | 2/14/2024 | APPLICANT |
| Disabled Access Plans Picked Up | 3/15/2024 | APPLICANT |
Permit Application Clearance Information
| DAS Clearance | Not Cleared | 1/27/2024 | Department of Building and Safety |
| Driveway location | Not Cleared | 1/27/2024 | Department of Transportation |
| Fire Marshal Fire Life Safety | Not Cleared | 1/27/2024 | Los Angeles Fire Department |
| Green Code | Not Cleared | 1/27/2024 | Department of Building and Safety |
| Hydrant and Access approval | Not Cleared | 1/27/2024 | Los Angeles Fire Department |
| Low Impact Development (LID) | Not Cleared | 1/27/2024 | Bureau of Sanitation |
| Permit | Not Cleared | 1/27/2024 | Bureau of Engineering |
| Roof/Waste drainage to street | Not Cleared | 1/27/2024 | Bureau of Engineering |
| Sewer availability | Not Cleared | 1/27/2024 | Bureau of Engineering |
| Specific Plan | Not Cleared | 1/27/2024 | Department of Transportation |
| Trees in Parkway | Not Cleared | 1/27/2024 | Bureau of Street Services |
| Zoning Clearance | Not Cleared | 1/27/2024 | Department of Building and Safety |
| Frnt yard landscape/Water mgmt | Not Cleared | 2/5/2024 | City Planning Department |
| Miscellaneous | Not Cleared | 2/5/2024 | Bureau of Engineering |
| Opn space landscape/Water mgmt | Not Cleared | 2/5/2024 | City Planning Department |
| SB8 RUD | Not Cleared | 2/5/2024 | Los Angeles Housing Department |
| Specific Plan | Not Cleared | 2/5/2024 | City Planning Department |
| ZI | Not Cleared | 2/5/2024 | City Planning Department |
| ZI | Not Cleared | 2/5/2024 | City Planning Department |
| Address approval | Cleared | 2/28/2024 | DINAH GARIN |
| Highway dedication | Not Cleared | 2/28/2024 | Bureau of Engineering |
| Eng Process Fee Ord 176,300 | Cleared | 3/1/2024 | DINAH GARIN |
| Bicycle Parking | Not Cleared | 3/6/2024 | Bureau of Engineering |
| Bicycle Parking | Not Cleared | 3/6/2024 | Department of Transportation |
| Miscellaneous | Cleared | 3/13/2024 | DALIA MOKAYED |
| Building over 36-ft | Cleared | 3/18/2024 | CALOSHA APPROVED |
| Excavation more than 5-ft deep | Cleared | 3/18/2024 | CALOSHA APPROVED |
| Grading Pre-Inspection | Cleared | 3/21/2024 | JOE VO |