1368-1368 1/2 E 33RD ST 90011
Certificate Information: 1368-1368 1/2 E 33RD ST 90011
- Application / Permit
- 24010-10000-00181
- Plan Check / Job No.
- B24LA00821
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 3-STORY SFD WITH ATTACHED ADU PER LAMC 12.22A.33(c)-(d) AND ATTACHED 1-CAR GARAGE AT REAR OF LOT NFPA 13D SOLAR INSTALLATION REQUIRED TO MEET 4.45KW PER TITLE 24 PRIOR TO COFO
- Permit Issued
- Issued on 5/21/2025
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/23/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/17/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/1/2024 | VIVIAN LAO |
| Corrections Issued | 2/7/2024 | VIVIAN LAO |
| Quality Review Completed | 2/9/2024 | KEN GILL |
| Building Plans Picked Up | 2/14/2024 | APPLICANT |
| Plan Check Approved | 5/23/2024 | VIVIAN LAO |
| Issued | 5/21/2025 | APPLICANT |
| CofO in Progress | 2/20/2026 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 2/23/2026 | DEROLD HAUFF |
| Permit Finaled | 2/23/2026 | DEROLD HAUFF |
| CofO Issued | 2/23/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/22/2024 | WALLIE JONG |
| Address approval | Cleared | 3/27/2024 | JUSTIN BICOL |
| Hydrant and Access approval | Cleared | 3/27/2024 | MATTHEW CRAIG |
| SB8 RUD | Cleared | 3/29/2024 | KEVIN SCHULTZ |
| Sewer availability | Cleared | 4/1/2024 | JUSTIN BICOL |
| Low Impact Development (LID) | Cleared | 4/8/2024 | PATRICK LOPEZ |
| Roof/Waste drainage to street | Cleared | 4/9/2024 | JUSTIN BICOL |
| Historic Resource Verification | Cleared | 4/11/2024 | YASMINE BASHIRI |
| Redevelopment Project Area | Cleared | 4/11/2024 | YASMINE BASHIRI |
Contact Information
| Contractor | Lajoma Construction Inc; Lic. No.: 864461-B | PO BOX 39459 DOWNEY, CA 90241 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/2/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 6/2/2025 | Approved | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 6/12/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 6/13/2025 | Approved | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 7/16/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Deputy Wood Construction | 9/9/2025 | Conditional Approval | RONNIE MEDINA |
| Floor/Roof Diaphrgm/Shear Wall | 9/9/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 9/10/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 9/11/2025 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 9/11/2025 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 9/11/2025 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 9/12/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 9/12/2025 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 9/22/2025 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Rough | 9/22/2025 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 9/22/2025 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| Insulation | 9/26/2025 | Approved | ANTHONY RAMOS |
| Interior/Exterior Lathing | 9/26/2025 | Approved | ANTHONY RAMOS |
| Drywall Nailing | 10/2/2025 | Not Ready for Inspection | RONNIE MEDINA |
| Drywall Nailing | 10/6/2025 | Approved | ALEJANDRO DE ARTOLA |
| Pre-Inspection | 1/5/2026 | Approved | ALEJANDRO DE ARTOLA |
| Verify Rec and Parks Fee Memo | 1/5/2026 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 1/22/2026 | Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 1/22/2026 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Final | 2/3/2026 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 2/3/2026 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 2/3/2026 | Approved | ALEJANDRO DE ARTOLA |
| Verify Rec and Parks Fee Memo | 2/3/2026 | Approved | ALEJANDRO DE ARTOLA |
| Final | 2/13/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 2/13/2026 | SGSOV Not Required | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 2/13/2026 | Approved | ALEJANDRO DE ARTOLA |
| Final | 2/18/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 2/20/2026 | OK to Issue CofO | ALEJANDRO DE ARTOLA |