12225 W TWEED LANE 90049

Certificate Information: 12225 W TWEED LANE 90049

Application / Permit
24010-10000-00177
Plan Check / Job No.
B24LA00806
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
2) NEW DETACHED ONE STORY ADU AT REAR OF LOT. DETACHED ADU PER 65852.2 (e)(1)(B) and LAMC 12.22 A.33 (c)-(d), (g). FIRE SPRINKLERS NFPA 13D THROUGH OUT.
Permit Issued
Issued on 4/24/2024
Issuing Office
Current Status
CofO Issued on 9/11/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/17/2024 APPLICANT
Assigned to Plan Check Engineer 1/18/2024 ADRIANA LOPEZ
Corrections Issued 1/21/2024 ADRIANA LOPEZ
Quality Review Completed 1/26/2024 KEN GILL
Building Plans Picked Up 1/31/2024 APPLICANT
Applicant returned to address corrections 3/13/2024 ADRIANA LOPEZ
Applicant returned to address corrections 4/4/2024 ADRIANA LOPEZ
Applicant returned to address corrections 4/16/2024 ADRIANA LOPEZ
Plan Check Approved 4/16/2024 ADRIANA LOPEZ
No Progress 4/16/2024 ADRIANA LOPEZ
Plan Check Approved 4/24/2024 ADRIANA LOPEZ
Issued 4/24/2024 APPLICANT
CofO in Progress 8/1/2025 HERBERT GIRON
Permit Finaled 9/11/2025 RICHARD STEINBACH
CofO Issued 9/11/2025 RICHARD STEINBACH
Permit Finaled 9/11/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 2/16/2024 DARIN LAM
Construction near power lines Cleared 2/16/2024 WALTER RAMIREZ
Construction within easement Cleared 2/16/2024 WALTER RAMIREZ
Eng Process Fee Ord 176,300 Cleared 2/20/2024 DARIN LAM
Sewer availability Cleared 2/20/2024 DARIN LAM
Miscellaneous Cleared 3/1/2024 DAVID URITA
Low Impact Development (LID) Cleared 3/20/2024 ROGELIO CORTES
Hydrant and Access approval Cleared 3/23/2024 GILBERT URREA
Roof/Waste drainage to street Cleared 3/27/2024 VLADIMIR ARUTYUNYAN
Specific Plan Cleared 4/8/2024 FREDDY GARCIA
GPI Written Notices Cleared 4/16/2024 ADRIANA LOPEZ
Grading Pre-Inspection Cleared 4/16/2024 ADRIANA LOPEZ

Contact Information

Architect Leishman,, Thomas Edward; Lic. No.: C15059 28100 RIDGEFERN COURT      RANCHO PALOS VERDES, CA 90275
Contractor Owner-Builder       ,
Engineer Lin,, Chi Hsin; Lic. No.: GE2921 123 N VALENCIA ST      ALHAMBRA, CA 91801
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/15/2024 Partial Approval ARAM AVEDISIAN
Footing/Foundation/Slab 5/20/2024 Corrections Issued ARAM AVEDISIAN
Footing/Foundation/Slab 5/28/2024 Corrections Issued KENNETH NAGLE
Footing/Foundation/Slab 7/26/2024 Approved ARAM AVEDISIAN
ELECTRICAL-Rough 8/26/2024 Corrections Issued JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 8/26/2024 Corrections Issued JESUS RODRIGUEZ
HVAC-Rough 8/26/2024 Approved JESUS RODRIGUEZ
PLUMBING-Rough 8/26/2024 Corrections Issued JESUS RODRIGUEZ
BUILDING-Rough-Frame 9/3/2024 Approved JESUS RODRIGUEZ
Green Building Rough 9/3/2024 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 9/3/2024 Approved JESUS RODRIGUEZ
PLUMBING-Rough 9/3/2024 Approved JESUS RODRIGUEZ
Verify Sprinkler Sign Off 9/3/2024 Approved JESUS RODRIGUEZ
Insulation 9/6/2024 Approved JESUS RODRIGUEZ
Special/Order Compliance 9/6/2024 Partial Inspection MICHAEL ALLEN
Drywall Nailing 9/16/2024 Approved KENNETH NAGLE
Shower Pan 10/8/2024 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 12/11/2024 Partial Approval JESUS RODRIGUEZ
Final 5/14/2025 Corrections Issued HERBERT GIRON
Green Building Final 5/14/2025 Approved HERBERT GIRON
HVAC-Final 5/14/2025 Approved HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 5/14/2025 SGSOV Not Ready HERBERT GIRON
Smoke Detectors 5/14/2025 Not Ready for Inspection HERBERT GIRON
ELECTRICAL-Final 5/27/2025 Approved HERBERT GIRON
PLUMBING-Final 5/27/2025 Corrections Issued HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 5/27/2025 SGSOV Not Required HERBERT GIRON
Smoke Detectors 5/27/2025 Approved HERBERT GIRON
Final 7/9/2025 Corrections Issued HERBERT GIRON
PLUMBING-Final 7/9/2025 Not Ready for Inspection HERBERT GIRON
Service/Power Release 7/9/2025 Not Ready for Inspection HERBERT GIRON
PLUMBING-Final 7/11/2025 Approved HERBERT GIRON
Special/Order Compliance 7/11/2025 Corrections Issued HERBERT GIRON
Final 7/29/2025 Not Ready for Inspection HERBERT GIRON
Final 8/1/2025 OK to Issue CofO HERBERT GIRON
Service/Power Release 8/1/2025 Approved HERBERT GIRON