5036 N WOODLEY AVE 91436

Certificate Information: 5036 N WOODLEY AVE 91436

Application / Permit
24010-10000-00082
Plan Check / Job No.
B24LA00279
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan NEW 2-STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE. NFPA 13R FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 5/7/2024
Issuing Office
Current Status
CofO Issued on 8/28/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/8/2024 APPLICANT
Assigned to Plan Check Engineer 1/11/2024 MAHNAZ NOURHASHEMI
Corrections Issued 2/12/2024 MAHNAZ NOURHASHEMI
Quality Review Completed 2/13/2024 CHAD DOI
Applicant returned to address corrections 4/16/2024 SERGIO GUTIERREZ
Plan Check Approved 4/17/2024 MAHNAZ NOURHASHEMI
Issued 5/7/2024 APPLICANT
CofO in Progress 8/27/2025 SEAN WIRCH
Permit Finaled 8/28/2025 JOHN JANSON
CofO Issued 8/28/2025 JOHN JANSON
Permit Finaled 8/28/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 2/14/2024 LEE GUILBEAUX
Permit Cleared 2/14/2024 LEE GUILBEAUX
Sewer availability Cleared 2/14/2024 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 2/14/2024 LEE GUILBEAUX
ZA Case Cleared 2/15/2024 BRENNEN OBETO
ZA Case Cleared 2/15/2024 BRENNEN OBETO
Trees in Parkway Cleared 2/29/2024 ADALBERTO VERA
Eng Process Fee Ord 176,300 Cleared 3/28/2024 LEE GUILBEAUX
Hydrant and Access approval Cleared 3/29/2024 RUEL COLE
Low Impact Development (LID) Cleared 3/29/2024 ROGELIO CORTES
Roof/Waste drainage to street Cleared 4/1/2024 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/29/2024 Corrections Issued THOMAS FINNILA
PLUMBING-Rough 5/29/2024 Conditional Approval THOMAS FINNILA
Deputy Reinf. Concrete 6/3/2024 Conditional Approval HENRY KIM
Excavation/Setback/Form/Re-Bar 6/3/2024 Partial Approval THOMAS FINNILA
Pre-Inspection 6/11/2024 Corrections Issued THOMAS FINNILA
Footing/Foundation/Slab 6/13/2024 Approved THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 6/28/2024 Corrections Issued THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 7/24/2024 Corrections Issued THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 8/2/2024 Partial Inspection THOMAS FINNILA
Green Building Rough 8/2/2024 Not Ready for Inspection THOMAS FINNILA
Verify Sprinkler Sign Off 8/2/2024 Not Ready for Inspection THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 8/13/2024 Partial Approval THOMAS FINNILA
Deputy Wood Construction 8/15/2024 Conditional Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 8/27/2024 Not Ready for Inspection THOMAS FINNILA
HVAC-Rough 8/29/2024 Corrections Issued THOMAS FINNILA
PLUMBING-Rough 8/29/2024 Approved THOMAS FINNILA
ELECTRICAL-Rough 9/25/2024 Approved ALEXANDER HANDY
Floor/Roof Diaphrgm/Shear Wall 9/25/2024 Partial Approval ALEXANDER HANDY
HVAC-Rough 9/25/2024 Approved ALEXANDER HANDY
Shower Pan 10/4/2024 Approved ALEXANDER HANDY
BUILDING-Rough-Frame 10/15/2024 Corrections Issued THOMAS FINNILA
Green Building Rough 10/15/2024 Approved THOMAS FINNILA
Verify Sprinkler Sign Off 10/15/2024 Approved THOMAS FINNILA
Interior/Exterior Lathing 10/28/2024 Approved THOMAS FINNILA
BUILDING-Rough-Frame 10/30/2024 Approved MORRIS JACKSON
Insulation 10/30/2024 Approved MORRIS JACKSON
Drywall Nailing 11/25/2024 Approved SCOTT SOBEL
Sewer 3/4/2025 Approved THOMAS FINNILA
ELECTRICAL-Final 3/17/2025 Not Ready for Inspection THOMAS FINNILA
HVAC-Final 4/15/2025 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Final 4/17/2025 Corrections Issued THOMAS FINNILA
HVAC-Final 4/21/2025 Corrections Issued THOMAS FINNILA
PLUMBING-Final 5/23/2025 Approved THOMAS FINNILA
ELECTRICAL-Final 5/27/2025 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Final 5/28/2025 Approved MORRIS JACKSON
HVAC-Final 5/28/2025 Approved MORRIS JACKSON
Final 6/16/2025 Corrections Issued THOMAS FINNILA
Service/Power Release 6/16/2025 Not Ready for Inspection THOMAS FINNILA
Final 7/2/2025 Corrections Issued SEAN WIRCH
Green Building Final 7/2/2025 Approved SEAN WIRCH
SGSOV-Seismic Gas S/O Valve 7/2/2025 SGSOV Approved SEAN WIRCH
Service/Power Release 7/2/2025 Approved SEAN WIRCH
Smoke Detectors 7/2/2025 Approved SEAN WIRCH
Deputy Reinf. Concrete 8/27/2025 Partial Approval SEAN WIRCH
Final 8/27/2025 OK to Issue CofO SEAN WIRCH