5171 N CASPAR AVE 90041

Certificate Information: 5171 N CASPAR AVE 90041

Application / Permit
24010-10000-00052
Plan Check / Job No.
B23LA24655
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
ePlan***PROPOSED RECROOM WITH ATTACHED GARAGE
Permit Issued
Issued on 4/30/2025
Issuing Office
Current Status
Issued on 4/30/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/6/2024 APPLICANT
Assigned to Plan Check Engineer 2/8/2024 SINA KHOSRAVI
Corrections Issued 2/14/2024 SINA KHOSRAVI
Quality Review Completed 3/5/2024 CAROLYNN NEPOMUCENO
Applicant returned to address corrections 9/16/2024 SINA KHOSRAVI
Applicant returned to address corrections 3/12/2025 SINA KHOSRAVI
Applicant returned to address corrections 4/1/2025 SINA KHOSRAVI
Plan Check Approved 4/23/2025 SINA KHOSRAVI
Issued 4/30/2025 APPLICANT

Permit Application Clearance Information

Sewer availability Cleared 6/24/2024 JESSICA OPINION
Eng Process Fee Ord 176,300 Cleared 6/25/2024 JESSICA OPINION
Low Impact Development (LID) Cleared 2/20/2025 ERNEST TSE
Roof/Waste drainage to street Cleared 4/8/2025 JESSICA OPINION
Grading Pre-Inspection Cleared 4/23/2025 SINA KHOSRAVI

Contact Information

Contractor Owner-Builder       ,
Engineer Motavvef,, Nasser; Lic. No.: C40977 15335 MORRISON ST 370      SHERMAN OAKS, CA 91403

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/2/2025 Partial Approval ALIZAH MAYAGOITIA
Footing/Foundation/Slab 6/2/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Footing/Foundation/Slab 6/17/2025 Approved DAVID WILLIAMS
Excavation/Setback/Form/Re-Bar 7/8/2025 Approved DAVID WILLIAMS
Excavation/Setback/Form/Re-Bar 7/11/2025 Approved DAVID WILLIAMS
Reinforced Concrete Frame 7/11/2025 Approved DAVID WILLIAMS
Floor/Roof Diaphrgm/Shear Wall 8/12/2025 Corrections Issued JEFFREY MEAD
Wood Frame 8/12/2025 Not Ready for Inspection JEFFREY MEAD
Floor/Roof Diaphrgm/Shear Wall 8/25/2025 Partial Approval ALIZAH MAYAGOITIA
Wood Frame 8/25/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Interior/Exterior Lathing 9/4/2025 Approved DAVID WILLIAMS
BUILDING-Rough-Frame 9/29/2025 Approved DAVID WILLIAMS
ELECTRICAL-Rough 9/29/2025 Approved DAVID WILLIAMS
Green Building Rough 9/29/2025 Approved DAVID WILLIAMS
HVAC-Rough 9/29/2025 Approved DAVID WILLIAMS
PLUMBING-Rough 9/29/2025 Approved DAVID WILLIAMS
Verify Sprinkler Sign Off 9/29/2025 Approved DAVID WILLIAMS
Insulation 10/15/2025 Approved GEM DE OCAMPO
Drywall Nailing 10/21/2025 Approved RONNIE MEDINA
Final 1/7/2026 Corrections Issued RONNIE MEDINA
Green Building Final 1/7/2026 Not Ready for Inspection RONNIE MEDINA
SGSOV-Seismic Gas S/O Valve 1/7/2026 SGSOV Not Ready RONNIE MEDINA
Service/Power Release 1/7/2026 Not Ready for Inspection RONNIE MEDINA
Smoke Detectors 1/7/2026 Not Ready for Inspection RONNIE MEDINA