431 S CITRUS AVE 90036

Certificate Information: 431 S CITRUS AVE 90036

Application / Permit
24010-10000-00048
Plan Check / Job No.
B23LA24652
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New detached 2-story ADU
Permit Issued
Issued on 10/14/2024
Issuing Office
Current Status
Permit Closed on 7/22/2025
Certificate of Occupancy
Permit Closed More Information

Permit Application Status History

Submitted 1/31/2024 APPLICANT
Assigned to Plan Check Engineer 2/15/2024 JOE VO
Corrections Issued 2/23/2024 JOE VO
Quality Review Completed 2/23/2024 GARO TELMI
Plan Check Approved 6/28/2024 JOE VO
Issued 10/14/2024 APPLICANT
Permit Closed 7/21/2025 RONNIE MINDANAO

Permit Application Clearance Information

Address approval Cleared 3/27/2024 DAVID LOPEZ
Roof/Waste drainage to street Cleared 3/27/2024 DAVID LOPEZ
Sewer availability Cleared 3/27/2024 DAVID LOPEZ
Eng Process Fee Ord 176,300 Cleared 4/4/2024 DAVID LOPEZ
Construction near power lines Cleared 4/18/2024 RIDWAN HARDY
Hydrant and Access approval Cleared 5/1/2024 MATTHEW CRAIG

Contact Information

Architect Woodcraft,, Astra E; Lic. No.: NA32722       ,
Contractor R B Remodeling & Construction; Lic. No.: 905605-B       ,
Engineer Nester,, Melvin Russell; Lic. No.: C26324 2902 TYLER CT      SIMI VALLEY, CA 93063

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/19/2024 Corrections Issued RONNIE MINDANAO
METHANE-Subgrade 12/2/2024 Approved RONNIE MINDANAO
PLUMBING-Rough 12/2/2024 Approved RONNIE MINDANAO
Deputy Methane Barrier 12/3/2024 Conditional Approval RONNIE MINDANAO
Excavation/Setback/Form/Re-Bar 12/5/2024 Approved RONNIE MINDANAO
METHANE-Barrier 12/5/2024 Approved RONNIE MINDANAO
Floor/Roof Diaphrgm/Shear Wall 12/16/2024 Partial Approval JEFFREY MEAD
Floor/Roof Diaphrgm/Shear Wall 12/20/2024 Corrections Issued RONNIE MINDANAO
Deputy Drilled-In Anchors 1/7/2025 Conditional Approval RONNIE MINDANAO
Deputy Wood Construction 1/7/2025 Conditional Approval RONNIE MINDANAO
BUILDING-Rough-Frame 1/14/2025 Not Ready for Inspection RONNIE MINDANAO
Floor/Roof Diaphrgm/Shear Wall 1/14/2025 Not Ready for Inspection RONNIE MINDANAO
Green Building Rough 1/14/2025 Not Ready for Inspection RONNIE MINDANAO
METHANE-Rough 1/14/2025 Not Ready for Inspection RONNIE MINDANAO
PLUMBING-Rough 1/14/2025 Approved RONNIE MINDANAO
Verify Sprinkler Sign Off 1/14/2025 Not Ready for Inspection RONNIE MINDANAO
ELECTRICAL-Rough 1/29/2025 Approved RONNIE MINDANAO
HVAC-Rough 1/29/2025 Approved RONNIE MINDANAO
Floor/Roof Diaphrgm/Shear Wall 1/30/2025 Approved ENRIQUE MIRELES
Green Building Rough 1/30/2025 Approved ENRIQUE MIRELES
METHANE-Rough 1/30/2025 Not Ready for Inspection ENRIQUE MIRELES
Verify Sprinkler Sign Off 1/30/2025 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 3/12/2025 Approved RONNIE MINDANAO
BUILDING-Rough-Frame 3/13/2025 Conditional Approval RONNIE MINDANAO
METHANE-Rough 3/13/2025 Corrections Issued RONNIE MINDANAO
Insulation 3/18/2025 Approved RONNIE MINDANAO
Drywall Nailing 3/21/2025 Approved RONNIE MINDANAO
Interior/Exterior Lathing 3/26/2025 Approved RONNIE MINDANAO
Shower Pan 3/26/2025 Approved RONNIE MINDANAO
Sewer 4/10/2025 Partial Approval RONNIE MINDANAO
Underground Mechanical 4/10/2025 Approved RONNIE MINDANAO
Sewer 4/28/2025 Approved RONNIE MINDANAO
Underground Mechanical 4/28/2025 Approved RONNIE MINDANAO
BUILDING-Rough-Frame 6/20/2025 Conditional Approval RONNIE MINDANAO
ELECTRICAL-Final 6/20/2025 Corrections Issued RONNIE MINDANAO
Final 6/20/2025 Corrections Issued RONNIE MINDANAO
Footing/Foundation/Slab 6/20/2025 Approved RONNIE MINDANAO
Green Building Final 6/20/2025 Order to Comply Issued RONNIE MINDANAO
HVAC-Final 6/20/2025 Corrections Issued RONNIE MINDANAO
METHANE-Final 6/20/2025 Not Ready for Inspection RONNIE MINDANAO
METHANE-Rough 6/20/2025 Approved RONNIE MINDANAO
SGSOV-Seismic Gas S/O Valve 6/20/2025 SGSOV No Gas RONNIE MINDANAO
Service/Power Release 6/20/2025 Not Ready for Inspection RONNIE MINDANAO
Smoke Detectors 6/20/2025 Approved RONNIE MINDANAO
BUILDING-Rough-Frame 7/16/2025 Approved RONNIE MINDANAO
Final 7/16/2025 Corrections Issued RONNIE MINDANAO
Green Building Final 7/16/2025 Approved RONNIE MINDANAO
METHANE-Final 7/16/2025 Approved RONNIE MINDANAO
METHANE-Rough 7/16/2025 Approved RONNIE MINDANAO
Service/Power Release 7/16/2025 Approved RONNIE MINDANAO
Final 7/21/2025 Permit Closed RONNIE MINDANAO