633 S BURLINGAME AVE 90049

Certificate Information: 633 S BURLINGAME AVE 90049

Application / Permit
23047-40000-01269
Plan Check / Job No.
B23SP00171
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
PROPOSED POOL AND SPA AT REAR OF LOT PER L.A. CITY STANDARD PLAN #268 WITH ENGINEER'S DETAILS.
Permit Issued
Issued on 9/8/2023
Issuing Office
Metro
Current Status
CofO Issued on 8/26/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/10/2023 APPLICANT
Assigned to Plan Check Engineer 8/24/2023 LAWRENCE QUIRANTE
Corrections Issued 8/31/2023 LAWRENCE QUIRANTE
Building Plans Picked Up 8/31/2023 APPLICANT
Plan Check Approved 9/7/2023 CRISTINA SALAZAR
Issued 9/8/2023 APPLICANT
CofO in Progress 7/31/2024 KIRK SANDERS
Permit Finaled 8/26/2024 RICHARD STEINBACH
CofO Issued 8/26/2024 RICHARD STEINBACH
Permit Finaled 8/26/2024 RICHARD STEINBACH

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Intex Design And Construction Oc Inc; Lic. No.: 1073000-B 2646 DUPONT DR STE 60 #348      IRVINE, CA 92612
Engineer Lacher,, Todd Lee; Lic. No.: C67656 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/30/2024 Approved ARAM AVEDISIAN
Grounding or Bonding 1/30/2024 Partial Approval ARAM AVEDISIAN
Pool Piping 1/30/2024 Approved ARAM AVEDISIAN
Pre-Gunite 1/30/2024 Conditional Approval ARAM AVEDISIAN
Deputy Shotcrete 1/31/2024 Conditional Approval ASHLEY THOMPSON
Deputy Shotcrete 2/1/2024 Conditional Approval EVAN COOPER
Enclosure/Fence 6/24/2024 Corrections Issued KIRK SANDERS
Enclosure/Fence 6/28/2024 Approved KIRK SANDERS
Equipment Noise Level 7/3/2024 Approved EUSEBIO GUZMAN
Final 7/3/2024 Corrections Issued KIRK SANDERS
Pre-Gunite 7/3/2024 Not Ready for Inspection KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 7/3/2024 SGSOV Not Ready KIRK SANDERS
ELECTRICAL-Final 7/5/2024 Approved EVAN COOPER
PLUMBING-Final 7/5/2024 Approved EVAN COOPER
ELECTRICAL-Final 7/9/2024 Corrections Issued KIRK SANDERS
Final 7/9/2024 Corrections Issued KIRK SANDERS
PLUMBING-Final 7/9/2024 Approved KIRK SANDERS
Pre-Gunite 7/9/2024 Approved KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 7/9/2024 SGSOV Approved KIRK SANDERS
ELECTRICAL-Final 7/17/2024 Corrections Issued KIRK SANDERS
Final 7/17/2024 Corrections Issued KIRK SANDERS
PLUMBING-Final 7/17/2024 Approved KIRK SANDERS
Final 7/20/2024 Partial Approval SEAN HAUPT
Final 7/23/2024 Corrections Issued SEAN HAUPT
Final 7/31/2024 OK to Issue CofO KIRK SANDERS