10453 W SANDAL LANE 90077

Certificate Information: 10453 W SANDAL LANE 90077

Application / Permit
23047-30000-01957
Plan Check / Job No.
B23WL03134
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW SWIMMING POOL AND SPA PER ENG CALS AND PLANS ON PILE ** 3 OF 4 **
Permit Issued
Issued on 4/22/2025
Issuing Office
West Los Angeles
Current Status
Issued on 4/22/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/22/2023 APPLICANT
Assigned to Plan Check Engineer 1/3/2024 KAVIAN REFAHI
Corrections Issued 1/6/2024 KAVIAN REFAHI
Building Plans Picked Up 1/16/2024 APPLICANT
Quality Review Completed 1/17/2024 REZA HAGHIGHAT
Applicant returned to address corrections 6/14/2024 KAVIAN REFAHI
Applicant returned to address corrections 9/16/2024 KAVIAN REFAHI
Applicant returned to address corrections 12/20/2024 KAVIAN REFAHI
Applicant returned to address corrections 3/28/2025 KAVIAN REFAHI
Plan Check Approved 4/21/2025 KAVIAN REFAHI
Issued 4/22/2025 APPLICANT

Permit Application Clearance Information

ZA Case Cleared 8/6/2024 JAZMIN ROQUE
Grading Pre-Inspection Cleared 3/19/2025 KAVIAN REFAHI

Contact Information

Contractor Owner-Builder       ,
Engineer Masterman,, Gary Clyde; Lic. No.: GE567 1766 EAGLE RIDGE CIR      WICHITA FALLS, TX 76309
Engineer Roberts,, Jeffrey Allan; Lic. No.: C56881 8325 FOOTHILL BLVD. STE A      SUNLAND, CA 91040
Geologist Schick,, John Wayne; Lic. No.: EG1300 7650 HASKELL AVENUE STE D      VAN NUYS, CA 91406

Inspector Information

RYAN SALAZAR, (310) 914-3862 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 6/16/2025 Partial Approval CHRISTOPHER WILSON
Deputy Other (see comments) 6/17/2025 Conditional Approval CHRISTOPHER WILSON
Deputy Other (see comments) 9/19/2025 Conditional Approval CHRISTOPHER WILSON
Pre-Gunite 9/19/2025 Partial Approval CHRISTOPHER WILSON
Deputy Other (see comments) 9/22/2025 Conditional Approval CHRISTOPHER WILSON
Deputy Shotcrete 10/22/2025 Partial Approval SEAN HAUPT
Excavation/Setback/Form/Re-Bar 10/27/2025 Approved SEAN HAUPT
Pre-Gunite 10/27/2025 Approved SEAN HAUPT
Rough-Plumbing 10/27/2025 Partial Approval SEAN HAUPT
Deputy Shotcrete 11/4/2025 Conditional Approval ANDREW NAVE
Deck 1/7/2026 Approved CHRISTOPHER WILSON
Grounding or Bonding 1/7/2026 Partial Approval CHRISTOPHER WILSON