169 N SALTAIR AVE 90049
Certificate Information: 169 N SALTAIR AVE 90049
- Application / Permit
- 23047-30000-01503
- Plan Check / Job No.
- B23WL02383
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- (N) Pool and SPA Per standard plan # 265.
- Permit Issued
- Issued on 5/16/2024
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 10/14/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/21/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/28/2023 | JAHANSHAH POURHASSAN |
| Corrections Issued | 9/28/2023 | JAHANSHAH POURHASSAN |
| Plan Check Approved | 11/15/2023 | ALFREDO JARA |
| Issued | 5/16/2024 | APPLICANT |
| CofO in Progress | 10/14/2025 | CARLOS MATAMOROS |
| Permit Finaled | 10/14/2025 | RICHARD STEINBACH |
| CofO Issued | 10/14/2025 | RICHARD STEINBACH |
| Permit Finaled | 10/14/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 9/28/2023 | JAHANSHAH POURHASSAN |
Contact Information
| Contractor | A&N Developments; Lic. No.: 1101931-B | 252 TRIANGLE ST THOUSAND OAKS, CA 91360 |
| Engineer | Tran,, Quang Tai; Lic. No.: C70929 | 355 N LANTANA ST 333 CAMARILLO, CA 93010 |
| Engineer | Zhang,, Yao; Lic. No.: C74572 | 538 ROCCO CIRCLE CORONA, CA 92882 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 7/3/2024 | Approved | CARLOS MATAMOROS |
| Deputy Shotcrete | 7/10/2024 | Conditional Approval | CHRISTOPHER WILSON |
| Deck | 5/19/2025 | Approved | BOBBY KEY |
| Pre-Inspection | 6/11/2025 | No Access for Inspection | CARLOS MATAMOROS |
| Pre-Inspection | 6/12/2025 | Partial Inspection | ARAM AVEDISIAN |
| Enclosure/Fence | 7/8/2025 | Corrections Issued | SEAN HAUPT |
| Enclosure/Fence | 7/17/2025 | Approved | ARAM AVEDISIAN |
| Excavation/Setback/Form/Re-Bar | 9/26/2025 | Approved | CARLOS MATAMOROS |
| Final | 9/26/2025 | Corrections Issued | CARLOS MATAMOROS |
| PLUMBING-Final | 9/26/2025 | Approved | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 9/26/2025 | SGSOV Approved | CARLOS MATAMOROS |
| Pool Equipment Noise Test | 9/30/2025 | Not Ready for Inspection | EUSEBIO GUZMAN |
| Final | 10/2/2025 | OK to Issue CofO | CARLOS MATAMOROS |
| ELECTRICAL-Final | 10/7/2025 | Approved | CARLOS MATAMOROS |