1850 S BENECIA AVE 90025

Certificate Information: 1850 S BENECIA AVE 90025

Application / Permit
23047-30000-01465
Plan Check / Job No.
B23WL02316
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
New swimming pool and baja at rear of the lot
Permit Issued
Issued on 12/19/2023
Issuing Office
Current Status
CofO Issued on 7/7/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/14/2023 APPLICANT
Assigned to Plan Check Engineer 9/14/2023 REZA HAGHIGHAT
Corrections Issued 9/14/2023 REZA HAGHIGHAT
Plan Check Approved 12/19/2023 REZA HAGHIGHAT
Issued 12/19/2023 APPLICANT
CofO in Progress 4/7/2025 DANIEL VERA
Permit Finaled 7/7/2025 RICHARD STEINBACH
CofO Issued 7/7/2025 RICHARD STEINBACH
Permit Finaled 7/7/2025 RICHARD STEINBACH

Permit Application Clearance Information

Construction near power lines Cleared 12/11/2023 RIDWAN HARDY
Grading Pre-Inspection Cleared 12/19/2023 REZA HAGHIGHAT

Contact Information

Contractor Eskan Builders Corp; Lic. No.: 1023638-B 19451 SHERMAN WAY UNIT 506      RESEDA, CA 91335
Engineer Smith,, Melvin Bruce; Lic. No.: GE2673 2165 N MARVEL AVE      SIMI VALLEY, CA 93065
Engineer Zhang,, Yao; Lic. No.: C74572 538 ROCCO CIRCLE      CORONA, CA 92882

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Gas Piping or Gas Test 3/22/2024 Approved STEPHANIE SWANSON
Gas Piping or Gas Test 3/27/2024 Approved STEPHANIE SWANSON
Pool Piping 6/24/2024 Approved STEPHANIE SWANSON
Pre-Gunite 6/24/2024 Corrections Issued STEPHANIE SWANSON
Rough-Electrical 6/24/2024 Approved STEPHANIE SWANSON
Rough-Plumbing 6/24/2024 Approved STEPHANIE SWANSON
Deputy Shotcrete 6/26/2024 Conditional Approval STEPHANIE SWANSON
Grounding or Bonding 8/2/2024 Not Ready for Inspection STEPHANIE SWANSON
Grounding or Bonding 8/5/2024 Approved CHRISTOPHER WILSON
Enclosure/Fence 9/10/2024 Approved STEPHANIE SWANSON
Pool Equipment Noise Test 10/3/2024 Approved ANDEY CHAPARRO
Excavation/Setback/Form/Re-Bar 10/8/2024 Approved STEPHANIE SWANSON
Final 10/8/2024 Corrections Issued STEPHANIE SWANSON
Pre-Gunite 10/8/2024 Approved STEPHANIE SWANSON
SGSOV-Seismic Gas S/O Valve 10/8/2024 SGSOV Not Ready STEPHANIE SWANSON
SGSOV-Seismic Gas S/O Valve 3/28/2025 SGSOV Not Ready BOBBY KEY
Final 4/3/2025 OK to Issue CofO DANIEL VERA
SGSOV-Seismic Gas S/O Valve 4/3/2025 SGSOV Approved DANIEL VERA