623 N LUCERNE BLVD 90004
Certificate Information: 623 N LUCERNE BLVD 90004
- Application / Permit
- 23047-30000-00833
- Plan Check / Job No.
- B23WL01360
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- New pool and spa per city standard plan and Engineer's design.
- Permit Issued
- Issued on 7/31/2023
- Issuing Office
- Current Status
- CofO Issued on 5/22/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/22/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/25/2023 | CAROLEAN BASMA |
| Corrections Issued | 5/31/2023 | CAROLEAN BASMA |
| Quality Review Completed | 5/31/2023 | CHIHARU SUZUKI |
| Building Plans Picked Up | 6/1/2023 | APPLICANT |
| Applicant returned to address corrections | 6/2/2023 | CAROLEAN BASMA |
| Plan Check Approved | 7/25/2023 | CAROLEAN BASMA |
| Issued | 7/31/2023 | APPLICANT |
| CofO in Progress | 5/21/2024 | JEFFREY MEAD |
| Permit Finaled | 5/22/2024 | DEROLD HAUFF |
| CofO Issued | 5/22/2024 | DEROLD HAUFF |
| Permit Finaled | 5/22/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Architect | Takacs,, David Alexander; Lic. No.: C33737 | 824 S. LOS ANGELES STREET LOS ANGELES, CA 90014 |
| Contractor | Owner-Builder | , |
| Engineer | Biedenbach,, Christopher James; Lic. No.: C74003 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/4/2023 | Approved | JEFFREY MEAD |
| Gas Piping or Gas Test | 8/4/2023 | Not Ready for Inspection | JEFFREY MEAD |
| Grading Pre-Inspection | 8/4/2023 | Not Ready for Inspection | JEFFREY MEAD |
| Pool Piping | 8/4/2023 | Approved | JEFFREY MEAD |
| Pre-Gunite | 8/4/2023 | Approved | JEFFREY MEAD |
| Rough-Electrical | 8/4/2023 | Not Ready for Inspection | JEFFREY MEAD |
| Rough-Plumbing | 8/4/2023 | Not Ready for Inspection | JEFFREY MEAD |
| Final | 4/2/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| SGSOV-Seismic Gas S/O Valve | 4/2/2024 | SGSOV Not Ready | AMIR NAZARIAN |
| Enclosure/Fence | 4/4/2024 | Corrections Issued | JEFFREY MEAD |
| Final | 4/4/2024 | Corrections Issued | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 4/4/2024 | SGSOV Not Ready | JEFFREY MEAD |
| Enclosure/Fence | 4/23/2024 | Approved | JEFFREY MEAD |
| Grounding or Bonding | 4/23/2024 | Approved | JEFFREY MEAD |
| Pool Equipment Noise Test | 4/25/2024 | Approved | JUAN ESCOTO DELGADO |
| ELECTRICAL-Final | 5/9/2024 | Approved | JEFFREY MEAD |
| Final | 5/9/2024 | Partial Approval | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 5/9/2024 | SGSOV Approved | JEFFREY MEAD |
| Final | 5/21/2024 | OK to Issue CofO | JEFFREY MEAD |