120 S GLENROY AVE 90049

Certificate Information: 120 S GLENROY AVE 90049

Application / Permit
23047-30000-00532
Plan Check / Job No.
B23WL00843
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
New swimming pool and spa within the pool at rear of the lot
Permit Issued
Issued on 10/22/2024
Issuing Office
West Los Angeles
Current Status
Issued on 10/22/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/30/2023 APPLICANT
Assigned to Plan Check Engineer 4/6/2023 REZA HAGHIGHAT
Corrections Issued 4/13/2023 REZA HAGHIGHAT
Quality Review Completed 4/25/2023 KAVIAN REFAHI
Building Plans Picked Up 4/27/2023 APPLICANT
Applicant returned to address corrections 6/5/2023 REZA HAGHIGHAT
Applicant returned to address corrections 8/2/2023 REZA HAGHIGHAT
Plan Check Approved 10/18/2023 REZA HAGHIGHAT
Issued 10/22/2024 APPLICANT

Permit Application Clearance Information

Grading Pre-Inspection Cleared 10/18/2023 REZA HAGHIGHAT

Contact Information

Architect , ; Lic. No.: C35626 607 VIA LOS MIRADORES      REDONDO BEACH, CA 90277
Contractor C & C Partners Design/Build Firm Inc; Lic. No.: 654337-B 508 N PACIFIC COAST HWY      REDONDO BEACH, CA 90277
Engineer Garcia,, Lionel J; Lic. No.: C58475 24702 NARBONNE AVE      LOMITA, CA 90717
Engineer Soto,, Miguel Angel; Lic. No.: C87493 653 W 5TH ST      SAN PEDRO, CA 90731
Engineer Zhang,, Yao; Lic. No.: C74572 538 ROCCO CIRCLE      CORONA, CA 92882
Geologist , ; Lic. No.: GEO841 PO BOX 8133      HUNTINGTON BEACH, CA 92615

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Gunite 4/9/2025 Not Ready for Inspection CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 7/14/2025 Approved MEL KHACHATOURIAN
Grounding or Bonding 7/14/2025 Partial Approval MEL KHACHATOURIAN
Pool Piping 7/14/2025 Approved MEL KHACHATOURIAN
Pre-Gunite 7/14/2025 Approved MEL KHACHATOURIAN
Rough-Electrical 7/14/2025 Partial Approval MEL KHACHATOURIAN
Rough-Plumbing 7/14/2025 Partial Approval MEL KHACHATOURIAN
Deputy Shotcrete 7/16/2025 Conditional Approval MICHAEL PELHAM
ELECTRICAL-Final 7/29/2025 Conditional Approval BOBBY KEY
PLUMBING-Final 7/29/2025 Corrections Issued BOBBY KEY
Grounding or Bonding 10/28/2025 Approved CARLOS MATAMOROS
Enclosure/Fence 11/26/2025 Approved CARLOS MATAMOROS
Enclosure/Fence 12/3/2025 Approved CHRISTOPHER WILSON
Final 3/2/2026 Conditional Approval EVAN COOPER
SGSOV-Seismic Gas S/O Valve 3/2/2026 SGSOV Approved EVAN COOPER
Final 3/3/2026 Conditional Approval EVAN COOPER