160 N TIGERTAIL ROAD 90049

Certificate Information: 160 N TIGERTAIL ROAD 90049

Application / Permit
23047-30000-00473
Plan Check / Job No.
B23WL00770
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
New pool with spa within the pool and infinity basin on piles
Permit Issued
Issued on 10/19/2023
Issuing Office
West Los Angeles
Current Status
Issued on 10/19/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/29/2023 APPLICANT
Assigned to Plan Check Engineer 4/13/2023 REZA HAGHIGHAT
Corrections Issued 4/16/2023 REZA HAGHIGHAT
Quality Review Completed 4/25/2023 KAVIAN REFAHI
Building Plans Picked Up 4/28/2023 APPLICANT
Plan Check Approved 10/17/2023 REZA HAGHIGHAT
Issued 10/19/2023 APPLICANT

Permit Application Clearance Information

ZA Case Cleared 4/21/2023 SPENCER WEJROWSKI
Grading Pre-Inspection Cleared 10/17/2023 REZA HAGHIGHAT

Contact Information

Contractor Blue Label Construction Inc; Lic. No.: 972011-B 2632 WILSHIRE BLVD #363      SANTA MONICA, CA 90403
Engineer Daneshfar,, Kourosh Dan; Lic. No.: C68377 19722 ARMINTA ST      WINNETKA, CA 91306
Engineer Zhang,, Yao; Lic. No.: C74572 538 ROCCO CIRCLE      CORONA, CA 92882
Geologist Feffer,, Joshua R; Lic. No.: EG2138 12253 GORHAM AVE      LOS ANGELES, CA 90049

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/12/2024 Partial Approval CARLOS MATAMOROS
Pre-Inspection 9/10/2024 Approved CARLOS MATAMOROS
Deputy Other (see comments) 9/26/2024 Conditional Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 9/26/2024 Partial Approval CARLOS MATAMOROS
Piling/Pier/Caisson 9/26/2024 Partial Approval CARLOS MATAMOROS
Deputy Other (see comments) 9/27/2024 Conditional Approval CARLOS MATAMOROS
Deputy Other (see comments) 1/28/2025 Conditional Approval CARLOS MATAMOROS
Piling/Pier/Caisson 1/29/2025 Approved CARLOS MATAMOROS
Pre-Gunite 1/29/2025 Partial Approval CARLOS MATAMOROS
Deputy Other (see comments) 1/31/2025 Conditional Approval CARLOS MATAMOROS
Deputy Shotcrete 3/6/2025 Conditional Approval CARLOS MATAMOROS
Pre-Gunite 3/6/2025 Approved STEPHANIE SWANSON
Rough-Electrical 3/6/2025 Partial Approval STEPHANIE SWANSON
Rough-Plumbing 3/6/2025 Partial Approval STEPHANIE SWANSON
Gas Piping or Gas Test 5/13/2026 Corrections Issued KEVIN SARGSYAN
Gas Piping or Gas Test 5/18/2026 Partial Approval EVAN COOPER