615 S BUNDY DR 90049
Certificate Information: 615 S BUNDY DR 90049
- Application / Permit
- 23047-30000-00347
- Plan Check / Job No.
- B23WL00542
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- New Pool 25' x 14' and Spa 8' x 6' per standard Plan #268
- Permit Issued
- Issued on 3/9/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 11/5/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/3/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/3/2023 | DAVID CASTILLO |
| Corrections Issued | 3/3/2023 | DAVID CASTILLO |
| Plan Check Approved | 3/9/2023 | EDWIN ESPIN |
| Issued | 3/9/2023 | APPLICANT |
| CofO in Progress | 10/30/2024 | JESUS RODRIGUEZ |
| Permit Finaled | 11/5/2024 | RICHARD STEINBACH |
| CofO Issued | 11/5/2024 | RICHARD STEINBACH |
| Permit Finaled | 11/5/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 3/3/2023 | DAVID CASTILLO |
Contact Information
| Contractor | Horusicky Construction Inc; Lic. No.: 309844-C53 | P O BOX 3789 PALOS VERDES, CA 90274 |
| Engineer | Biscombe,, Lauren; Lic. No.: C86501 | 900 WILSHIRE BLVD 19TH FLOOR LOS ANGELES, CA 90017 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 5/5/2023 | Corrections Issued | KEVIN SARGSYAN |
| Pool Piping | 5/11/2023 | Approved | JESUS RODRIGUEZ |
| Pre-Gunite | 5/11/2023 | Approved | JESUS RODRIGUEZ |
| Deputy Shotcrete | 5/19/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Enclosure/Fence | 7/20/2023 | Corrections Issued | KEVIN SARGSYAN |
| Enclosure/Fence | 7/21/2023 | Approved | OGANES TARAKHCHYAN |
| Grounding or Bonding | 7/21/2023 | Approved | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 9/6/2024 | Approved | JESUS RODRIGUEZ |
| Final | 9/6/2024 | Conditional Approval | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 9/6/2024 | SGSOV Approved | JESUS RODRIGUEZ |
| Special/Order Compliance | 9/6/2024 | Partial Inspection | MICHAEL ALLEN |
| ELECTRICAL-Final | 10/29/2024 | Approved | JESUS RODRIGUEZ |
| Final | 10/29/2024 | OK to Issue CofO | JESUS RODRIGUEZ |