294 N BELLINO DR 90272

Certificate Information: 294 N BELLINO DR 90272

Application / Permit
23047-30000-00113
Plan Check / Job No.
B23WL00156
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
New swimming pool and spa and concrete deck on piles at rear of the lot
Permit Issued
Issued on 8/8/2023
Issuing Office
West Los Angeles
Current Status
CofO Issued on 11/21/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/20/2023 APPLICANT
Assigned to Plan Check Engineer 2/7/2023 REZA HAGHIGHAT
Corrections Issued 2/8/2023 REZA HAGHIGHAT
Quality Review Completed 2/16/2023 KAVIAN REFAHI
Plan Check Approved 7/11/2023 REZA HAGHIGHAT
Issued 8/8/2023 APPLICANT
CofO in Progress 11/17/2025 BOBBY KEY
Permit Finaled 11/21/2025 RICHARD STEINBACH
CofO Issued 11/21/2025 RICHARD STEINBACH
Permit Finaled 11/21/2025 RICHARD STEINBACH

Permit Application Clearance Information

Coastal Zone Cleared 6/8/2023 JASON CHAN
ZA Case Cleared 6/8/2023 JASON CHAN
ZA Case Cleared 6/8/2023 JASON CHAN
ZA Case Cleared 6/8/2023 JASON CHAN
Grading Pre-Inspection Cleared 7/11/2023 REZA HAGHIGHAT

Contact Information

Contractor A R T E Construction & Development Inc; Lic. No.: 974107-B 350 E ALHAMBRA RD      ALHAMBRA, CA 91801
Engineer Azizisefat,, Solayman; Lic. No.: C57840 19510 VENTURA BLVD STE 110      TARZANA, CA 91356
Geologist Carrle,, Conrad Henry; Lic. No.: EG2359 23128 WILDWOOD ROAD      NEWHALL, CA 91321

Inspector Information

DANIEL VERA, (213) 577-9924 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/27/2023 Partial Approval EVAN COOPER
Piling/Pier/Caisson 10/27/2023 Partial Approval EVAN COOPER
Deputy Other (see comments) 10/31/2023 Conditional Approval EVAN COOPER
Excavation/Setback/Form/Re-Bar 11/13/2023 Partial Approval EVAN COOPER
Piling/Pier/Caisson 11/13/2023 Approved EVAN COOPER
Deputy Other (see comments) 11/15/2023 No Access for Inspection KENNETH NAGLE
Pre-Gunite 5/1/2024 Approved EVAN COOPER
Deputy Other (see comments) 5/8/2024 Conditional Approval EVAN COOPER
Deputy Shotcrete 5/8/2024 Conditional Approval EVAN COOPER
Deck 5/13/2024 Approved EVAN COOPER
Grounding or Bonding 5/13/2024 Partial Approval EVAN COOPER
Enclosure/Fence 5/22/2024 Approved EVAN COOPER
Pool Equipment Noise Test 7/2/2024 Approved EUSEBIO GUZMAN
SGSOV-Seismic Gas S/O Valve 7/12/2024 SGSOV Not Ready EVAN COOPER
Excavation/Setback/Form/Re-Bar 7/15/2024 Approved EVAN COOPER
Final 7/15/2024 Corrections Issued EVAN COOPER
SGSOV-Seismic Gas S/O Valve 7/15/2024 SGSOV Approved EVAN COOPER
Final 11/17/2025 OK to Issue CofO BOBBY KEY