13674 W BAYLISS ROAD 90049
Certificate Information: 13674 W BAYLISS ROAD 90049
- Application / Permit
- 23047-20001-00158
- Plan Check / Job No.
- B23LA21201
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- SUPPLEMENTAL PERMIT TO 23047-10000-00158 TO REVISE POOL PLANS AND POOL DECK
- Permit Issued
- Issued on 1/16/2024
- Issuing Office
- Current Status
- Permit Finaled on 6/25/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/9/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/16/2023 | SELLA BENYAMIN |
| Corrections Issued | 11/21/2023 | SELLA BENYAMIN |
| Quality Review Completed | 11/27/2023 | STEVEN KIM |
| Applicant returned to address corrections | 12/22/2023 | SELLA BENYAMIN |
| Plan Check Approved | 1/12/2024 | SELLA BENYAMIN |
| No Progress | 1/12/2024 | SELLA BENYAMIN |
| Plan Check Approved | 1/12/2024 | SELLA BENYAMIN |
| Issued | 1/16/2024 | APPLICANT |
| Permit Finaled | 6/25/2025 | KEVIN SARGSYAN |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
| Engineer | Berkoz,, Ertunga; Lic. No.: S2504 | 4665 ELLENITA AVE TARZANA, CA 91356 |
Inspector Information
| KEVIN SARGSYAN, (310) 914-3889 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/13/2024 | Partial Approval | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 3/27/2024 | Corrections Issued | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 3/28/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 3/29/2024 | Partial Approval | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 4/19/2024 | Partial Approval | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 4/24/2024 | Partial Approval | KEVIN SARGSYAN |
| Pool Piping | 6/17/2024 | Partial Approval | KEVIN SARGSYAN |
| Pre-Gunite | 6/17/2024 | Conditional Approval | KEVIN SARGSYAN |
| Grounding or Bonding | 4/8/2025 | Approved | KEVIN SARGSYAN |