14457 W HERRON ST 91342
Certificate Information: 14457 W HERRON ST 91342
- Application / Permit
- 23047-20000-01949
- Plan Check / Job No.
- B23VN17545
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- EPLAN New Pool and spa per standard plan
- Permit Issued
- Issued on 3/6/2024
- Issuing Office
- Current Status
- CofO Issued on 7/2/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/23/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/26/2023 | KHUONG TRUONG |
| Corrections Issued | 12/26/2023 | KHUONG TRUONG |
| Applicant returned to address corrections | 3/6/2024 | ZAW HAN |
| Plan Check Approved | 3/6/2024 | ZAW HAN |
| Issued | 3/6/2024 | APPLICANT |
| CofO in Progress | 6/14/2024 | JENNIFER RABUCHIN |
| CofO Issued | 7/2/2024 | RUBEN SALAS |
| Permit Finaled | 7/2/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Construction near power lines | Cleared | 2/28/2024 | RIDWAN HARDY |
| Construction within easement | Cleared | 2/28/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Rg Pools Spa & General Construction Inc; Lic. No.: 752775-B | , |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 3/19/2024 | Partial Approval | JENNIFER RABUCHIN |
| Deputy Shotcrete | 3/26/2024 | Conditional Approval | ROBERT GOLD |
| Gas Piping or Gas Test | 3/26/2024 | Approved | JENNIFER RABUCHIN |
| Deck | 4/30/2024 | Approved | JENNIFER RABUCHIN |
| Enclosure/Fence | 5/24/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Pool Equipment Noise Test | 6/11/2024 | Approved | FELIPE PENICHE |
| ELECTRICAL-Final | 6/12/2024 | Approved | JENNIFER RABUCHIN |
| Enclosure/Fence | 6/12/2024 | Approved | JENNIFER RABUCHIN |
| Excavation/Setback/Form/Re-Bar | 6/12/2024 | Approved | JENNIFER RABUCHIN |
| Final | 6/12/2024 | OK to Issue CofO | JENNIFER RABUCHIN |
| Pre-Gunite | 6/12/2024 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 6/12/2024 | SGSOV Approved | JENNIFER RABUCHIN |