20531 W OVERLOOK CT 91326

Certificate Information: 20531 W OVERLOOK CT 91326

Application / Permit
23047-20000-01830
Plan Check / Job No.
B23VN16320
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 18'-0" X 34'-0" POOL WITH 10'-0" X 10'-0" SPA AND 8'-0" X 8'-10" FIRE PIT - PER LA CITY STANDARD PLAN 270 AND SUPPLEMENTARY ENGINEERED DETAIL
Permit Issued
Issued on 3/7/2024
Issuing Office
Valley
Current Status
CofO in Progress on 6/9/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/30/2023 APPLICANT
Assigned to Plan Check Engineer 11/30/2023 DANIEL ABRAMYAN
Corrections Issued 11/30/2023 DANIEL ABRAMYAN
Applicant returned to address corrections 2/1/2024 ISIS ARGUETA
Issued 3/7/2024 APPLICANT
CofO in Progress 6/9/2025 STEVEN BACK
CofO in Progress 6/17/2025 STEVEN BACK

Permit Application Clearance Information

Grading Pre-Inspection Cleared 11/30/2023 DANIEL ABRAMYAN
"T" removal Cleared 1/25/2024 STEVEN WECHSLER
ZA Case Cleared 1/25/2024 STEVEN WECHSLER
ZA Case Cleared 1/25/2024 STEVEN WECHSLER
Miscellaneous Cleared 3/7/2024 STEVEN WECHSLER

Contact Information

Contractor Owner-Builder       ,
Engineer Cristescu,, Barbu Dan; Lic. No.: C72038 14401 SYLVAN STREET 209      VAN NUYS, CA 91401

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Gunite 4/12/2024 Approved STEVEN BACK
Deputy Shotcrete 4/22/2024 Conditional Approval STEVEN BACK
Gas Piping or Gas Test 5/9/2024 Approved JEFFREY PARD
Deck 5/15/2024 Approved JEFFREY PARD
Grounding or Bonding 5/15/2024 Approved JEFFREY PARD
Enclosure/Fence 8/30/2024 Corrections Issued STEVEN BACK
Enclosure/Fence 10/4/2024 Approved JEFFREY PARD
Pool Equipment Noise Test 3/7/2025 Approved FELIPE PENICHE
Excavation/Setback/Form/Re-Bar 6/9/2025 Approved STEVEN BACK
Final 6/9/2025 Corrections Issued STEVEN BACK
SGSOV-Seismic Gas S/O Valve 6/9/2025 SGSOV Approved STEVEN BACK
Special/Order Compliance 6/16/2025 Partial Inspection GERMAN RODRIGUEZ MENDOZA
Final 6/17/2025 Corrections Issued STEVEN BACK