4251 N FORMAN AVE 91602
Certificate Information: 4251 N FORMAN AVE 91602
- Application / Permit
- 23047-20000-01819
- Plan Check / Job No.
- B23VN16202
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- ePlan: New Swimming Pool, Spa and Sunk-In Fire Pit
- Permit Issued
- Issued on 2/6/2024
- Issuing Office
- Current Status
- CofO Issued on 1/29/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/27/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/27/2023 | JOHNPAUL ISIP |
| Assigned to Plan Check Engineer | 11/27/2023 | JOHNPAUL ISIP |
| Corrections Issued | 11/30/2023 | JOHNPAUL ISIP |
| Applicant returned to address corrections | 1/18/2024 | CAROLEAN BASMA |
| Plan Check Approved | 1/26/2024 | CAROLEAN BASMA |
| Issued | 2/6/2024 | APPLICANT |
| CofO in Progress | 1/16/2026 | JAVIER RAMOS JR |
| Permit Finaled | 1/29/2026 | RUBEN SALAS |
| CofO Issued | 1/29/2026 | RUBEN SALAS |
| Permit Finaled | 1/29/2026 | RUBEN SALAS |
Permit Application Clearance Information
| ZI | Cleared | 1/19/2024 | ASHLEY RODARTE |
| ZA Case | Cleared | 1/22/2024 | ASHLEY RODARTE |
| ZA Case | Cleared | 1/22/2024 | ASHLEY RODARTE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Zhang,, Yao; Lic. No.: C74572 | 538 ROCCO CIRCLE CORONA, CA 92882 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Gas Piping or Gas Test | 6/28/2024 | Partial Inspection | SALVADOR MARTINEZ |
| Grounding or Bonding | 6/28/2024 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Pool Piping | 6/28/2024 | Partial Inspection | SALVADOR MARTINEZ |
| Pre-Gunite | 6/28/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Rough-Electrical | 6/28/2024 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Rough-Plumbing | 6/28/2024 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Gas Piping or Gas Test | 7/2/2024 | Approved | CHRISTOPHER ROJAS |
| Grounding or Bonding | 7/2/2024 | Approved | CHRISTOPHER ROJAS |
| Pool Piping | 7/2/2024 | Approved | CHRISTOPHER ROJAS |
| Pre-Inspection | 7/2/2024 | Approved | CHRISTOPHER ROJAS |
| Rough-Electrical | 7/2/2024 | Approved | CHRISTOPHER ROJAS |
| Rough-Plumbing | 7/2/2024 | Approved | CHRISTOPHER ROJAS |
| Deputy Shotcrete | 8/9/2024 | Conditional Approval | ROBERT GOLD |
| Gas Piping or Gas Test | 4/11/2025 | Approved | JAVIER RAMOS JR |
| Grounding or Bonding | 4/28/2025 | Approved | JAVIER RAMOS JR |
| Pool Equipment Noise Test | 7/29/2025 | Approved | FELIPE PENICHE |
| Enclosure/Fence | 8/22/2025 | Corrections Issued | JAVIER RAMOS JR |
| Enclosure/Fence | 8/29/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 8/29/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Final | 8/29/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Pre-Gunite | 8/29/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 8/29/2025 | SGSOV Not Ready | MISAEL ESPARZA |
| Enclosure/Fence | 9/3/2025 | Partial Inspection | JAVIER RAMOS JR |
| Enclosure/Fence | 1/15/2026 | Approved | JAVIER RAMOS JR |
| Excavation/Setback/Form/Re-Bar | 1/15/2026 | Approved | JAVIER RAMOS JR |
| Final | 1/15/2026 | OK to Issue CofO | JAVIER RAMOS JR |
| Pre-Gunite | 1/15/2026 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 1/15/2026 | SGSOV Approved | JAVIER RAMOS JR |