4633-4635 N BURNET AVE 91403

Certificate Information: 4633-4635 N BURNET AVE 91403

Application / Permit
23047-20000-01797
Plan Check / Job No.
B23VN16002
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 14' X 27' SWIMMING POOL W/ BAJA AND 9' X 8' SPA PER LA CITY STANDARD PLAN No. 268
Permit Issued
Issued on 12/8/2023
Issuing Office
Valley
Current Status
CofO Issued on 9/21/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/20/2023 APPLICANT
Assigned to Plan Check Engineer 11/20/2023 LUISANGEL VALENZUELA
Corrections Issued 11/20/2023 LUISANGEL VALENZUELA
Plan Check Approved 12/8/2023 GIOVANNY CHAVEZ
Issued 12/8/2023 APPLICANT
CofO in Progress 5/13/2024 THOMAS FINNILA
Permit Finaled 9/21/2024 DANIEL ORRANTE
CofO Issued 9/21/2024 DANIEL ORRANTE
Permit Finaled 9/21/2024 DANIEL ORRANTE

Permit Application Clearance Information

Construction near power lines Cleared 12/1/2023 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/15/2023 Conditional Approval THOMAS FINNILA
Grading Pre-Inspection 12/15/2023 Approved THOMAS FINNILA
Pre-Gunite 12/15/2023 Approved THOMAS FINNILA
Rough-Electrical 12/15/2023 Approved THOMAS FINNILA
Rough-Plumbing 12/15/2023 Approved THOMAS FINNILA
Deputy Shotcrete 12/18/2023 Conditional Approval JUAN VALENZUELA
Grounding or Bonding 3/1/2024 Partial Approval MISAEL ESPARZA
Enclosure/Fence 4/24/2024 Corrections Issued THOMAS FINNILA
Enclosure/Fence 4/26/2024 Corrections Issued THOMAS FINNILA
Enclosure/Fence 4/30/2024 Approved MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 5/6/2024 Approved THOMAS FINNILA
Final 5/6/2024 Corrections Issued THOMAS FINNILA
Pool Equipment Noise Test 5/6/2024 Approved ALFREDO FLORES
Grading Pre-Inspection 5/8/2024 Not Ready for Inspection THOMAS FINNILA
Final 5/10/2024 OK to Issue CofO THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 5/10/2024 SGSOV Approved THOMAS FINNILA