24419 W CLEAR CREEK PL 91304

Certificate Information: 24419 W CLEAR CREEK PL 91304

Application / Permit
23047-20000-01757
Plan Check / Job No.
B23VN15612
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
(N) IRR. SHAPED 27'-3" X 43'-6" SWIMMING POOL AND IRR. SHAPED 13'-6" X 9'-0" SPA PER LA STANDARD PLAN #268 AND SUPPLEMENTAL DETAIL
Permit Issued
Issued on 2/6/2024
Issuing Office
Valley
Current Status
CofO Issued on 8/13/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/13/2023 APPLICANT
Assigned to Plan Check Engineer 11/18/2023 SERGIO MUNIZ
Corrections Issued 11/18/2023 SERGIO MUNIZ
Building Plans Picked Up 12/28/2023 APPLICANT
Issued 2/6/2024 APPLICANT
CofO in Progress 8/2/2024 JEFFREY HARTLINE
Permit Finaled 8/13/2024 JOHN JANSON
CofO Issued 8/13/2024 JOHN JANSON
Permit Finaled 8/13/2024 JOHN JANSON

Permit Application Clearance Information

ZA Case Cleared 2/1/2024 SPENCER WEJROWSKI

Contact Information

Contractor Green Scene The; Lic. No.: 340258-C53 21220 DEVONSHIRE ST STE 102      CHATSWORTH, CA 91311
Engineer Biedenbach,, Christopher James; Lic. No.: C74003 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/15/2024 Corrections Issued CHRIS CHRISTENSEN
Grading Pre-Inspection 2/16/2024 Approved JEFFREY HARTLINE
Pre-Inspection 2/16/2024 Partial Approval JEFFREY HARTLINE
Pre-Gunite 3/5/2024 Approved JEFFREY HARTLINE
Rough-Electrical 3/5/2024 Approved JEFFREY HARTLINE
Rough-Plumbing 3/5/2024 Approved JEFFREY HARTLINE
Grounding or Bonding 4/12/2024 Approved JEFFREY HARTLINE
Enclosure/Fence 6/11/2024 Approved JEFFREY HARTLINE
Equipment Noise Level 7/17/2024 Approved AGUSTIN ALVAREZMORALES
Excavation/Setback/Form/Re-Bar 7/31/2024 Approved JEFFREY HARTLINE
Final 7/31/2024 Partial Approval JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 7/31/2024 SGSOV Approved JEFFREY HARTLINE
Final 8/2/2024 OK to Issue CofO JEFFREY HARTLINE