2337 N HIGH OAK DR 90068

Certificate Information: 2337 N HIGH OAK DR 90068

Application / Permit
23047-20000-01581
Plan Check / Job No.
B23VN13721
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
New swimming pool and spa to replace (e) pool and spa per city standard plan # 268
Permit Issued
Issued on 11/14/2023
Issuing Office
Valley
Current Status
CofO Issued on 11/24/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/5/2023 APPLICANT
Assigned to Plan Check Engineer 10/12/2023 HAYATO TSUCHIYA
Corrections Issued 10/12/2023 HAYATO TSUCHIYA
Building Plans Picked Up 10/16/2023 APPLICANT
Applicant returned to address corrections 10/31/2023 ALFRED RAMIREZ
Plan Check Approved 11/3/2023 REZA HAGHIGHAT
Issued 11/14/2023 APPLICANT
CofO in Progress 8/6/2024 ROY SPAULDING
Permit Finaled 11/24/2024 DEROLD HAUFF
Permit Finaled 11/24/2024 DEROLD HAUFF
CofO Issued 11/24/2024 DEROLD HAUFF

Permit Application Clearance Information

"D" conditions Cleared 10/25/2023 NATHAN ROMINE
CPC Cleared 10/25/2023 NATHAN ROMINE
ZI Cleared 10/25/2023 NATHAN ROMINE
Grading Pre-Inspection Cleared 11/3/2023 REZA HAGHIGHAT

Contact Information

Contractor Einfinite Designs Inc; Lic. No.: 959295-B 7602 SAN FERNANDO ROAD      SUN VALLEY, CA 91352
Engineer Lacher,, Todd Lee; Lic. No.: C67656 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/12/2024 Not Ready for Inspection ROY SPAULDING
Pre-Gunite 3/26/2024 Approved ROY SPAULDING
Rough-Electrical 3/26/2024 Approved ROY SPAULDING
Rough-Plumbing 3/26/2024 Approved ROY SPAULDING
Deputy Shotcrete 3/29/2024 Conditional Approval ROY SPAULDING
Deck 5/24/2024 Not Ready for Inspection BRIAN SULLIVAN
Grounding or Bonding 5/24/2024 Corrections Issued BRIAN SULLIVAN
Deck 5/29/2024 Corrections Issued ROY SPAULDING
Grounding or Bonding 5/29/2024 Approved ROY SPAULDING
Pre-Inspection 6/11/2024 Corrections Issued ROY SPAULDING
Enclosure/Fence 6/21/2024 Approved ROY SPAULDING
Equipment Noise Level 7/9/2024 Not Ready for Inspection ANDEY CHAPARRO
Pool Equipment Noise Test 7/9/2024 Not Ready for Inspection ANDEY CHAPARRO
SGSOV-Seismic Gas S/O Valve 7/10/2024 SGSOV Not Ready ROY SPAULDING
Equipment Noise Level 7/18/2024 Approved ANDEY CHAPARRO
Excavation/Setback/Form/Re-Bar 7/22/2024 Approved ROY SPAULDING
Final 7/22/2024 Corrections Issued ROY SPAULDING
SGSOV-Seismic Gas S/O Valve 7/22/2024 SGSOV Approved ROY SPAULDING
Final 7/29/2024 Corrections Issued BRIAN SULLIVAN
Final 8/1/2024 Corrections Issued CRAIG VAUGHAN
Final 8/5/2024 OK to Issue CofO ROY SPAULDING