16463 W BRYANT ST 91343
Certificate Information: 16463 W BRYANT ST 91343
- Application / Permit
- 23047-20000-01563
- Plan Check / Job No.
- B23VN13478
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- 16'-6" X 29'-6" SWIMMING POOL W/ 11'-6" X 8'-0" SPA PER STD PLAN # 254 & ENGINEERING DETAILS.
- Permit Issued
- Issued on 4/17/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/3/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/6/2023 | ARTIN ZARUKIAN |
| Corrections Issued | 10/7/2023 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 10/13/2023 | APPLICANT |
| Plan Check Approved | 4/17/2024 | ISIS ARGUETA |
| Issued | 4/17/2024 | APPLICANT |
| CofO in Progress | 10/15/2024 | SALVADOR MARTINEZ |
| Permit Finaled | 11/12/2024 | DANIEL ORRANTE |
| CofO Issued | 11/12/2024 | DANIEL ORRANTE |
| Permit Finaled | 11/12/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Construction near power lines | Cleared | 3/30/2024 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 4/4/2024 | CARLOS AGUILERA |
| Work Adjacent to Public Way | Cleared | 4/4/2024 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Azizisefat,, Solayman; Lic. No.: C57840 | 19510 VENTURA BLVD STE 110 TARZANA, CA 91356 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/30/2024 | Approved | SALVADOR MARTINEZ |
| Pre-Gunite | 5/7/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Pre-Gunite | 5/9/2024 | Approved | SALVADOR MARTINEZ |
| Deputy Shotcrete | 5/10/2024 | Conditional Approval | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 6/26/2024 | Not Ready for Inspection | RAUL OLAGI |
| Final | 6/26/2024 | Corrections Issued | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 6/26/2024 | SGSOV Not Ready | RAUL OLAGI |
| Deck | 7/9/2024 | Corrections Issued | RAUL OLAGI |
| Deck | 7/19/2024 | Approved | SALVADOR MARTINEZ |
| Enclosure/Fence | 8/28/2024 | Approved | RAUL OLAGI |
| Pool Equipment Noise Test | 9/12/2024 | Approved | FELIPE PENICHE |
| Excavation/Setback/Form/Re-Bar | 10/8/2024 | Approved | SALVADOR MARTINEZ |
| Final | 10/8/2024 | OK to Issue CofO | SALVADOR MARTINEZ |
| SGSOV-Seismic Gas S/O Valve | 10/8/2024 | SGSOV Approved | SALVADOR MARTINEZ |