1161 S STEARNS DR 90035
Certificate Information: 1161 S STEARNS DR 90035
- Application / Permit
- 23047-20000-01554
- Plan Check / Job No.
- B23VN13358
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 12'-0" X 20'-0" SWIMMING POOL PER STANDARD PLAN 268
- Permit Issued
- Issued on 10/17/2023
- Issuing Office
- Current Status
- CofO Issued on 6/14/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/29/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/29/2023 | ALFRED RAMIREZ |
| Corrections Issued | 9/29/2023 | ALFRED RAMIREZ |
| Plan Check Approved | 10/17/2023 | ALEC MOUSAKHANIAN |
| Issued | 10/17/2023 | APPLICANT |
| CofO in Progress | 5/23/2024 | ARTHUR NEGRETE |
| Permit Finaled | 6/14/2024 | DEROLD HAUFF |
| CofO Issued | 6/14/2024 | DEROLD HAUFF |
| Permit Finaled | 6/14/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| HPOZ | Cleared | 10/3/2023 | RYAN LY |
| ZI | Cleared | 10/3/2023 | RYAN LY |
| Historic monument | Cleared | 10/16/2023 | DEBORAH MCGILL |
Contact Information
| Contractor | Benabou Construction Inc; Lic. No.: 1034782-B | 1215 S POINT VIEW ST LOS ANGELES, CA 90035 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/30/2023 | Corrections Issued | JOSE AVILA |
| Rough-Electrical | 10/30/2023 | Partial Approval | JOSE AVILA |
| Rough-Plumbing | 10/30/2023 | Approved | JOSE AVILA |
| Deputy Shotcrete | 11/6/2023 | Conditional Approval | JOSE AVILA |
| Pre-Gunite | 11/6/2023 | Approved | JOSE AVILA |
| Gunite | 11/8/2023 | Approved | JOSE AVILA |
| Grounding or Bonding | 11/13/2023 | Approved | JOSE AVILA |
| Enclosure/Fence | 3/12/2024 | Approved | STUART CHAPMAN |
| Excavation/Setback/Form/Re-Bar | 3/21/2024 | Approved | STUART CHAPMAN |
| Final | 3/21/2024 | Corrections Issued | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 3/21/2024 | SGSOV Approved | STUART CHAPMAN |
| Final | 4/11/2024 | Corrections Issued | STUART CHAPMAN |
| Final | 5/9/2024 | Corrections Issued | JOAQUIN GREENOUGH |
| Pool Equipment Noise Test | 5/16/2024 | Not Ready for Inspection | JUAN ESCOTO DELGADO |
| Pre-Inspection | 5/17/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| Pool Equipment Noise Test | 5/21/2024 | Approved | JUAN ESCOTO DELGADO |
| Final | 5/22/2024 | OK to Issue CofO | ARTHUR NEGRETE |