2455 S OVERLAND AVE 90064
Certificate Information: 2455 S OVERLAND AVE 90064
- Application / Permit
- 23047-20000-01380
- Plan Check / Job No.
- B23VN11795
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- Apartment
- Primary Use
- (4) Pool/Spa - Public
- Work Description
- NEW 15' X 46' POOL IN (E) VAULT ON LEVEL 3 PER LA CITY STD 268 AND DETAIL 660
- Permit Issued
- Issued on 12/22/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/15/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/31/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/7/2023 | SELLA BENYAMIN |
| Disabled Access Plans Picked Up | 9/13/2023 | APPLICANT |
| Corrections Issued | 9/14/2023 | SELLA BENYAMIN |
| Quality Review Completed | 9/14/2023 | STEVEN KIM |
| Building Plans Picked Up | 9/22/2023 | APPLICANT |
| Plan Check Approved | 12/22/2023 | SELLA BENYAMIN |
| Issued | 12/22/2023 | APPLICANT |
| CofO in Progress | 10/2/2025 | DERRICK SPENCER |
| Permit Finaled | 10/15/2025 | DAVID TSAU |
| CofO Issued | 10/15/2025 | DAVID TSAU |
| Permit Finaled | 10/15/2025 | DAVID TSAU |
Permit Application Clearance Information
| DAS Clearance | Cleared | 12/6/2023 | OLLIE CARTER |
| Public Swimming Pool approval | Cleared | 12/22/2023 | LACDHS APPROVED |
Contact Information
| Contractor | Addison Pools Inc; Lic. No.: 753417-C53 | 4363 WOODMAN AVENUE SHERMAN OAKS, CA 91423 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| ROGELIO REYNA, (310) 914-3920 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| FLOOD-Proofing Certificate | 8/8/2024 | Not Ready for Inspection | PAUL DAVIDSON |
| METHANE-Rough | 8/8/2024 | Not Ready for Inspection | PAUL DAVIDSON |
| Pre-Gunite | 8/8/2024 | Partial Approval | PAUL DAVIDSON |
| Enclosure/Fence | 4/29/2025 | Approved | VASIL MIHALEV |
| Excavation/Setback/Form/Re-Bar | 8/1/2025 | Approved | DERRICK SPENCER |
| FLOOD-Proofing Certificate | 8/1/2025 | Approved | DERRICK SPENCER |
| Final | 8/1/2025 | Not Ready for Inspection | DERRICK SPENCER |
| METHANE-Barrier | 8/1/2025 | Approved | DERRICK SPENCER |
| METHANE-Rough | 8/1/2025 | Approved | DERRICK SPENCER |
| METHANE-Subgrade | 8/1/2025 | Approved | DERRICK SPENCER |
| Pre-Gunite | 8/1/2025 | Approved | DERRICK SPENCER |
| SGSOV-Seismic Gas S/O Valve | 8/1/2025 | SGSOV Approved | DERRICK SPENCER |
| Final | 8/12/2025 | Not Ready for Inspection | DERRICK SPENCER |
| Final | 10/2/2025 | OK to Issue CofO | DERRICK SPENCER |