22566 W MARGARITA DR 91364

Certificate Information: 22566 W MARGARITA DR 91364

Application / Permit
23047-20000-01362
Plan Check / Job No.
B23VN11627
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
REMODEL EX. SWIMMING POOL. ADD 12'X 8' SPA WITHIN POOL SHELL PER STANDARD PLAN #268 AND ENGINEER DETAILS.
Permit Issued
Issued on 9/6/2023
Issuing Office
Current Status
CofO Issued on 4/30/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/28/2023 APPLICANT
Assigned to Plan Check Engineer 8/28/2023 PINANK PATEL
Corrections Issued 8/28/2023 PINANK PATEL
Plan Check Approved 9/6/2023 ROSENDO MEDINA
Issued 9/6/2023 APPLICANT
CofO in Progress 3/14/2024 MORRIS JACKSON
Permit Finaled 4/30/2024 JOHN JANSON
CofO Issued 4/30/2024 JOHN JANSON
Permit Finaled 4/30/2024 JOHN JANSON

Permit Application Clearance Information

Specific Plan Cleared 8/31/2023 NATHAN ROMINE
ZI Cleared 8/31/2023 NATHAN ROMINE

Contact Information

Contractor Stanton Pools Inc; Lic. No.: 1009474-C53 P O BOX 6391      WESTLAKE VILLAGE, CA 91359
Engineer Thompson,, Matthew Gregory; Lic. No.: C86051 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

JOHN HAYES, (818) 774-4302 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Gas Piping or Gas Test 10/31/2023 Approved PETER FOLLING
Grounding or Bonding 10/31/2023 Not Ready for Inspection PETER FOLLING
Pool Piping 10/31/2023 Approved PETER FOLLING
Pre-Gunite 10/31/2023 Corrections Issued PETER FOLLING
Grounding or Bonding 11/3/2023 Approved SEAN HAUPT
Pre-Gunite 11/3/2023 Approved SEAN HAUPT
Deck 11/21/2023 Approved JOHN KIDWELL
Grounding or Bonding 11/21/2023 Approved JOHN KIDWELL
ELECTRICAL-Final 1/19/2024 Not Ready for Inspection JOHN KIDWELL
Enclosure/Fence 1/19/2024 Corrections Issued JOHN KIDWELL
PLUMBING-Final 1/19/2024 Not Ready for Inspection JOHN KIDWELL
Enclosure/Fence 2/29/2024 Approved JOHN KIDWELL
Equipment Noise Level 3/5/2024 Approved ALFREDO FLORES
ELECTRICAL-Final 3/8/2024 Not Ready for Inspection MORRIS JACKSON
Final 3/8/2024 Corrections Issued MORRIS JACKSON
PLUMBING-Final 3/8/2024 Not Ready for Inspection MORRIS JACKSON
SGSOV-Seismic Gas S/O Valve 3/8/2024 SGSOV Not Ready MORRIS JACKSON
ELECTRICAL-Final 3/12/2024 Approved MORRIS JACKSON
Final 3/12/2024 OK to Issue CofO MORRIS JACKSON
PLUMBING-Final 3/12/2024 Approved MORRIS JACKSON
SGSOV-Seismic Gas S/O Valve 3/12/2024 SGSOV Approved MORRIS JACKSON
Enclosure/Fence 4/22/2024 Approved MORRIS JACKSON
Enclosure/Fence 4/24/2024 Approved MORRIS JACKSON