6376 W MARYLAND DR 90048
Certificate Information: 6376 W MARYLAND DR 90048
- Application / Permit
- 23047-20000-01351
- Plan Check / Job No.
- B23VN11546
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 16'-11" x 26'-0" SWIMMING POOL AND 9'-0" x 9'-0" SPA PER STANDARD PLAN # 268.
- Permit Issued
- Issued on 1/25/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/3/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/25/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/25/2023 | GIOVANNY CHAVEZ |
| Corrections Issued | 8/25/2023 | GIOVANNY CHAVEZ |
| Applicant returned to address corrections | 8/29/2023 | ALEC MOUSAKHANIAN |
| Issued | 1/25/2024 | APPLICANT |
| CofO in Progress | 6/28/2024 | MEL KHACHATOURIAN |
| Permit Finaled | 7/3/2024 | DANIEL ORRANTE |
| CofO Issued | 7/3/2024 | DANIEL ORRANTE |
| Permit Finaled | 7/3/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Construction near power lines | Cleared | 1/20/2024 | RIDWAN HARDY |
| Construction within easement | Cleared | 1/20/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Biedenbach,, Christopher James; Lic. No.: C74003 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/23/2024 | Corrections Issued | MEL KHACHATOURIAN |
| Grounding or Bonding | 2/23/2024 | Partial Approval | MEL KHACHATOURIAN |
| Pool Piping | 2/23/2024 | Partial Approval | MEL KHACHATOURIAN |
| Rough-Electrical | 2/23/2024 | Partial Approval | MEL KHACHATOURIAN |
| Rough-Plumbing | 2/23/2024 | Partial Approval | MEL KHACHATOURIAN |
| Excavation/Setback/Form/Re-Bar | 2/27/2024 | Approved | MEL KHACHATOURIAN |
| Grounding or Bonding | 2/27/2024 | Approved | MEL KHACHATOURIAN |
| Pool Piping | 2/27/2024 | Approved | MEL KHACHATOURIAN |
| Rough-Electrical | 2/27/2024 | Approved | MEL KHACHATOURIAN |
| Rough-Plumbing | 2/27/2024 | Approved | MEL KHACHATOURIAN |
| Deck | 3/13/2024 | Approved | MEL KHACHATOURIAN |
| Grounding or Bonding | 3/13/2024 | Approved | MEL KHACHATOURIAN |
| Final | 5/21/2024 | Corrections Issued | MEL KHACHATOURIAN |
| Pre-Gunite | 5/21/2024 | Approved | MEL KHACHATOURIAN |
| SGSOV-Seismic Gas S/O Valve | 5/21/2024 | SGSOV Not Ready | MEL KHACHATOURIAN |
| Enclosure/Fence | 5/31/2024 | Partial Approval | MEL KHACHATOURIAN |
| SGSOV-Seismic Gas S/O Valve | 5/31/2024 | SGSOV Approved | MEL KHACHATOURIAN |
| Final | 6/6/2024 | OK to Issue CofO | MEL KHACHATOURIAN |