174 S GREENFIELD AVE 90049

Certificate Information: 174 S GREENFIELD AVE 90049

Application / Permit
23047-20000-01346
Plan Check / Job No.
B23VN11488
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 32' X 14' SWIMMING POOL AND 7' x 7' SPA PER LA CITY STANDARD PLAN #268
Permit Issued
Issued on 8/31/2023
Issuing Office
Valley
Current Status
CofO Issued on 5/1/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/24/2023 APPLICANT
Assigned to Plan Check Engineer 8/24/2023 KAMYAR EMAMI
Corrections Issued 8/24/2023 KAMYAR EMAMI
Plan Check Approved 8/31/2023 GURUNATH NESARAJAH
Issued 8/31/2023 APPLICANT
CofO in Progress 4/5/2025 MICHAEL PELHAM
Permit Finaled 5/1/2025 RICHARD STEINBACH
CofO Issued 5/1/2025 RICHARD STEINBACH
Permit Finaled 5/1/2025 RICHARD STEINBACH

Permit Application Clearance Information

Watercourse Cleared 8/29/2023 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 8/30/2023 JASON NG

Contact Information

Contractor Sam'S Pool Service & Construction; Lic. No.: 1041757-C53 P O BOX 2702      WINNETKA, CA 91396
Engineer Thompson,, Matthew Gregory; Lic. No.: C86051 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/15/2023 Approved CARLOS MATAMOROS
FLOOD-Proofing Certificate 9/15/2023 Approved CARLOS MATAMOROS
Grounding or Bonding 9/15/2023 Approved CARLOS MATAMOROS
Pool Piping 9/15/2023 Approved CARLOS MATAMOROS
Pre-Gunite 9/15/2023 Approved CARLOS MATAMOROS
Rough-Plumbing 9/15/2023 Approved CARLOS MATAMOROS
Deputy Shotcrete 9/25/2023 Conditional Approval MICHAEL PELHAM
Grounding or Bonding 1/23/2024 Approved CARLOS MATAMOROS
Enclosure/Fence 4/5/2024 Approved CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 3/7/2025 SGSOV Not Ready CARLOS MATAMOROS
Equipment Noise Level 3/11/2025 Approved ANDEY CHAPARRO
Pool Equipment Noise Test 3/11/2025 Approved ANDEY CHAPARRO
Final 3/18/2025 No Access for Inspection CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 3/18/2025 SGSOV Not Ready CARLOS MATAMOROS
Final 3/20/2025 Corrections Issued CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 3/20/2025 SGSOV Approved CARLOS MATAMOROS
ELECTRICAL-Final 3/24/2025 Approved CARLOS MATAMOROS
Final 3/24/2025 OK to Issue CofO CARLOS MATAMOROS