1349 S ALLENFORD AVE 90049
Certificate Information: 1349 S ALLENFORD AVE 90049
- Application / Permit
- 23047-20000-01318
- Plan Check / Job No.
- B23VN11135
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 32' X 17' POOL AND 7' x 7' SPA PER STANDARD PLAN #268
- Permit Issued
- Issued on 8/23/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/6/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/18/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/18/2023 | ISIS ARGUETA |
| Corrections Issued | 8/18/2023 | ISIS ARGUETA |
| Plan Check Approved | 8/23/2023 | ISIS ARGUETA |
| Issued | 8/23/2023 | APPLICANT |
| CofO in Progress | 3/6/2025 | KENNETH NAGLE |
| CofO Issued | 3/6/2025 | RICHARD STEINBACH |
| Permit Finaled | 3/6/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Designer Custom Pools Inc; Lic. No.: 1086707-C53 | 3749 E COLORADO BLVD PASADENA, CA 91107 |
| Engineer | Thompson,, Matthew Gregory; Lic. No.: C86051 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 8/28/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Rough-Electrical | 8/28/2024 | Approved | JESUS RODRIGUEZ |
| Rough-Plumbing | 8/28/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Gas Piping or Gas Test | 9/5/2024 | Approved | JESUS RODRIGUEZ |
| Pre-Gunite | 9/5/2024 | Conditional Approval | JESUS RODRIGUEZ |
| Rough-Electrical | 9/5/2024 | Approved | JESUS RODRIGUEZ |
| Rough-Plumbing | 9/5/2024 | Approved | JESUS RODRIGUEZ |
| Pre-Gunite | 9/20/2024 | Conditional Approval | JESUS RODRIGUEZ |
| Deck | 11/13/2024 | Approved | ARAM AVEDISIAN |
| Enclosure/Fence | 2/5/2025 | Approved | JESUS RODRIGUEZ |
| Pool Equipment Noise Test | 2/18/2025 | Approved | JAMES VORHIS |
| ELECTRICAL-Final | 2/19/2025 | Approved | JESUS RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 2/19/2025 | Approved | JESUS RODRIGUEZ |
| Final | 2/19/2025 | Partial Approval | JESUS RODRIGUEZ |
| Pre-Gunite | 2/19/2025 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 2/19/2025 | SGSOV Approved | JESUS RODRIGUEZ |
| Final | 3/6/2025 | OK to Issue CofO | KENNETH NAGLE |