5527 W HOMESIDE AVE 90016
Certificate Information: 5527 W HOMESIDE AVE 90016
- Application / Permit
- 23047-20000-01309
- Plan Check / Job No.
- B23VN11074
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- (N) POOL AND SPA PER CITY STD PLAN W/ SUPPL ENGR DETAIL
- Permit Issued
- Issued on 1/31/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/2/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/17/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/23/2023 | SERGIO MUNIZ |
| Corrections Issued | 8/24/2023 | SERGIO MUNIZ |
| Building Plans Picked Up | 8/30/2023 | APPLICANT |
| Plan Check Approved | 1/31/2024 | ALEC MOUSAKHANIAN |
| Issued | 1/31/2024 | APPLICANT |
| CofO in Progress | 5/1/2024 | AMIR NAZARIAN |
| Permit Finaled | 5/2/2024 | DEROLD HAUFF |
| CofO Issued | 5/2/2024 | DEROLD HAUFF |
| Permit Finaled | 5/2/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction within easement | Cleared | 1/24/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Aldan Construction & Remodeling Inc; Lic. No.: 1030243-B | 8549 WILSHIRE BLVD #1458 BEVERLY HILLS, CA 90211 |
| Engineer | Biedenbach,, Christopher James; Lic. No.: C74003 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/4/2024 | Approved | STUART CHAPMAN |
| Gas Piping or Gas Test | 3/4/2024 | Approved | STUART CHAPMAN |
| Grounding or Bonding | 3/4/2024 | Partial Approval | STUART CHAPMAN |
| Pre-Gunite | 3/4/2024 | Approved | STUART CHAPMAN |
| Rough-Electrical | 3/4/2024 | Approved | STUART CHAPMAN |
| Rough-Plumbing | 3/4/2024 | Approved | STUART CHAPMAN |
| Grounding or Bonding | 3/12/2024 | Approved | STUART CHAPMAN |
| Enclosure/Fence | 3/28/2024 | Approved | STUART CHAPMAN |
| Final | 4/10/2024 | Corrections Issued | AMIR NAZARIAN |
| SGSOV-Seismic Gas S/O Valve | 4/10/2024 | SGSOV Not Ready | AMIR NAZARIAN |
| Final | 4/15/2024 | Corrections Issued | AMIR NAZARIAN |
| SGSOV-Seismic Gas S/O Valve | 4/15/2024 | SGSOV Approved | AMIR NAZARIAN |
| Final | 4/19/2024 | Corrections Issued | AMIR NAZARIAN |
| Final | 4/30/2024 | OK to Issue CofO | AMIR NAZARIAN |