5304 N FORBES AVE 91436
Certificate Information: 5304 N FORBES AVE 91436
- Application / Permit
- 23047-20000-01267
- Plan Check / Job No.
- B23VN10719
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 21' X 16' POOL PER STANDARD PLAN 268 & ENGINEER DETAIL
- Permit Issued
- Issued on 1/9/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/7/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/10/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/10/2023 | ALEC MOUSAKHANIAN |
| Corrections Issued | 8/10/2023 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 1/9/2024 | ALEC MOUSAKHANIAN |
| Issued | 1/9/2024 | APPLICANT |
| CofO in Progress | 7/1/2024 | THOMAS FINNILA |
| Permit Finaled | 8/7/2024 | JOHN JANSON |
| CofO Issued | 8/7/2024 | JOHN JANSON |
| Permit Finaled | 8/7/2024 | JOHN JANSON |
Permit Application Clearance Information
| Construction near power lines | Cleared | 11/21/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Aqua Care; Lic. No.: 927181-C53 | 537 SOMBRERO RD MONROVIA, CA 91016 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/29/2024 | Approved | MORRIS JACKSON |
| Excavation/Setback/Form/Re-Bar | 2/14/2024 | Approved | VINCENT HANLEY |
| Pool Piping | 2/14/2024 | Approved | VINCENT HANLEY |
| Pre-Gunite | 2/14/2024 | Approved | VINCENT HANLEY |
| Deputy Shotcrete | 2/16/2024 | Partial Approval | VINCENT HANLEY |
| Deck | 4/12/2024 | Approved | VINCENT HANLEY |
| Enclosure/Fence | 4/23/2024 | Approved | VINCENT HANLEY |
| Rough-Electrical | 4/23/2024 | Approved | VINCENT HANLEY |
| Rough-Plumbing | 4/23/2024 | Approved | VINCENT HANLEY |
| Final | 5/17/2024 | Corrections Issued | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 5/17/2024 | SGSOV Not Ready | THOMAS FINNILA |
| Pool Equipment Noise Test | 6/25/2024 | Approved | FELIPE PENICHE |
| Final | 6/27/2024 | OK to Issue CofO | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 6/27/2024 | SGSOV Approved | THOMAS FINNILA |