1325 S WYCLIFF AVE 90732
Certificate Information: 1325 S WYCLIFF AVE 90732
- Application / Permit
- 23047-20000-01151
- Plan Check / Job No.
- B23VN09612
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- (N) 20'-0" X 12'-0" POOL WITH 6'-0" X 12'-0" SPA PER STANDARD PLAN 268
- Permit Issued
- Issued on 9/19/2023
- Issuing Office
- Valley
- Current Status
- Issued on 9/19/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/19/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/19/2023 | ALEC MOUSAKHANIAN |
| Corrections Issued | 7/19/2023 | ALEC MOUSAKHANIAN |
| Issued | 9/19/2023 | APPLICANT |
Permit Application Clearance Information
| Hold | Cleared | 9/14/2023 | MARIA VENDIVIL |
| Construction near power lines | Cleared | 9/19/2023 | TINA MIRANDA |
Contact Information
| Contractor | Mr Carlos Pools And Construction Inc; Lic. No.: 385622-C53 | 978 NORTH AMEILA AVE SAN DIMAS, CA 91773 |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Shotcrete | 10/10/2023 | Conditional Approval | JAMES CHAVEZ |
| Pre-Gunite | 11/21/2023 | No Access for Inspection | JAMES CHAVEZ |
| Pre-Gunite | 11/27/2023 | Corrections Issued | EUGENE CASSIDY |
| Pool Piping | 12/6/2023 | Corrections Issued | JAMES CHAVEZ |
| Excavation/Setback/Form/Re-Bar | 12/13/2023 | Approved | JAMES CHAVEZ |
| Pool Piping | 12/13/2023 | Approved | JAMES CHAVEZ |
| Pre-Gunite | 12/13/2023 | Approved | JAMES CHAVEZ |
| SGSOV-Seismic Gas S/O Valve | 12/13/2023 | SGSOV Not Ready | JAMES CHAVEZ |
| Final | 12/19/2023 | No Access for Inspection | JAMES CHAVEZ |
| SGSOV-Seismic Gas S/O Valve | 12/19/2023 | SGSOV Not Ready | JAMES CHAVEZ |
| Deputy Shotcrete | 12/21/2023 | Conditional Approval | JAMES CHAVEZ |
| Enclosure/Fence | 6/20/2024 | Approved | ANSON MAGLASANG |
| Final | 7/26/2024 | Corrections Issued | JAMES CHAVEZ |
| SGSOV-Seismic Gas S/O Valve | 7/26/2024 | SGSOV Not Required | JAMES CHAVEZ |
| Final | 8/7/2024 | Corrections Issued | JOSEPH MCGARRY |