200 N GUNSTON DR 90049

Certificate Information: 200 N GUNSTON DR 90049

Application / Permit
23047-20000-01137
Plan Check / Job No.
B23VN09530
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 53' X 22' SWIMMING POOL WITH 9' X 10' SPA, BAJA, AND AUTOMATIC POOL COVER VAULT WITHIN PER LA CITY STANDARD PLAN #268 AND ENGINEER DETAIL.
Permit Issued
Issued on 8/11/2023
Issuing Office
Current Status
CofO Issued on 4/9/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/18/2023 APPLICANT
Assigned to Plan Check Engineer 7/21/2023 KAMYAR EMAMI
Corrections Issued 7/24/2023 KAMYAR EMAMI
Building Plans Picked Up 7/26/2023 APPLICANT
Issued 8/11/2023 APPLICANT
CofO in Progress 3/21/2025 CARLOS MATAMOROS
CofO Issued 4/9/2025 RICHARD STEINBACH
Permit Finaled 4/9/2025 RICHARD STEINBACH

Permit Application Clearance Information

Grading Pre-Inspection Cleared 7/24/2023 JEROME MAGAT PALMA
Tract Map conditions Cleared 8/3/2023 STEVEN WECHSLER
Waste Hauler Permit Cleared 8/11/2023 TA ANH

Contact Information

Contractor One Creative Group Inc; Lic. No.: 628294-B 1276 N SWEETZER AVE #6      WEST HOLLYWOOD, CA 90069
Engineer Thompson,, Matthew Gregory; Lic. No.: C86051 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/13/2023 Not Ready for Inspection CARLOS MATAMOROS
Pre-Gunite 9/13/2023 Not Ready for Inspection CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 9/20/2023 Approved CARLOS MATAMOROS
Grounding or Bonding 9/20/2023 Approved CARLOS MATAMOROS
Pre-Gunite 9/20/2023 Approved CARLOS MATAMOROS
Deputy Shotcrete 9/27/2023 Conditional Approval CARLOS MATAMOROS
Enclosure/Fence 12/18/2024 Not Ready for Inspection CARLOS MATAMOROS
Pre-Inspection 12/18/2024 Approved CARLOS MATAMOROS
Enclosure/Fence 12/24/2024 Approved CARLOS MATAMOROS
Final 1/27/2025 Not Ready for Inspection CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 1/27/2025 SGSOV Approved CARLOS MATAMOROS
Final 2/25/2025 Corrections Issued CARLOS MATAMOROS
ELECTRICAL-Final 3/11/2025 Approved CARLOS MATAMOROS
Final 3/11/2025 Partial Approval CARLOS MATAMOROS
Final 3/18/2025 OK to Issue CofO CARLOS MATAMOROS