5234 N NOBLE AVE 91411
Certificate Information: 5234 N NOBLE AVE 91411
- Application / Permit
- 23047-20000-01131
- Plan Check / Job No.
- B23VN09491
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- POOL REMODEL: ADD NEW 7' X 7' SPA & BAJA WITHIN (E) POOL PER STANDARD PLAN #268 AND ENGINEER DETAILS. RELOCATE POOL EQUIPMENT.
- Permit Issued
- Issued on 8/15/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/16/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/17/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/20/2023 | ALEC MOUSAKHANIAN |
| Corrections Issued | 7/21/2023 | ALEC MOUSAKHANIAN |
| Building Plans Picked Up | 7/25/2023 | APPLICANT |
| Plan Check Approved | 8/15/2023 | ISIS ARGUETA |
| Issued | 8/15/2023 | APPLICANT |
| CofO in Progress | 3/6/2024 | THOMAS FINNILA |
| Permit Finaled | 4/16/2024 | DANIEL ORRANTE |
| CofO Issued | 4/16/2024 | DANIEL ORRANTE |
| Permit Finaled | 4/16/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Construction near power lines | Cleared | 8/14/2023 | WALTER RAMIREZ |
Contact Information
| Contractor | J A B S Pools And Spas; Lic. No.: 936142-C53 | 8055 MATILIJA AVENUE PANORAMA CITY, CA 91402 |
| Engineer | Biedenbach,, Christopher James; Lic. No.: C74003 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 8/30/2023 | Not Ready for Inspection | THOMAS FINNILA |
| Pre-Gunite | 9/1/2023 | Corrections Issued | THOMAS FINNILA |
| Pre-Gunite | 9/6/2023 | Not Ready for Inspection | THOMAS FINNILA |
| Pre-Gunite | 9/12/2023 | Corrections Issued | THOMAS FINNILA |
| Pre-Gunite | 9/18/2023 | Approved | RYAN SALAZAR |
| Deputy Shotcrete | 9/21/2023 | Conditional Approval | JUAN VALENZUELA |
| Gas Piping or Gas Test | 10/30/2023 | Not Ready for Inspection | THOMAS FINNILA |
| Gas Piping or Gas Test | 11/2/2023 | Approved | THOMAS FINNILA |
| Deck | 12/13/2023 | Approved | THOMAS FINNILA |
| Enclosure/Fence | 1/24/2024 | Corrections Issued | THOMAS FINNILA |
| Enclosure/Fence | 2/1/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Enclosure/Fence | 2/12/2024 | Approved | THOMAS FINNILA |
| Equipment Noise Level | 2/15/2024 | Approved | FELIPE PENICHE |
| Pool Equipment Noise Test | 2/15/2024 | Approved | FELIPE PENICHE |
| Final | 2/20/2024 | Partial Inspection | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 2/20/2024 | SGSOV Approved | THOMAS FINNILA |
| ELECTRICAL-Final | 2/23/2024 | Approved | THOMAS FINNILA |
| PLUMBING-Final | 2/23/2024 | Approved | THOMAS FINNILA |
| Final | 3/1/2024 | Corrections Issued | THOMAS FINNILA |
| Final | 3/5/2024 | OK to Issue CofO | THOMAS FINNILA |