2669 N HUTTON DR 90210
Certificate Information: 2669 N HUTTON DR 90210
- Application / Permit
- 23047-20000-00995
- Plan Check / Job No.
- B23VN08214
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- PROPOSED NEW 34'-4" X 17'-4" SWIMMING POOL W/ SPA PER CITY STD PLAN #268 & SUPPLEMENTAL ENGR DETAILS.
- Permit Issued
- Issued on 2/8/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/3/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/21/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/23/2023 | HAYATO TSUCHIYA |
| Corrections Issued | 6/24/2023 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 6/26/2023 | APPLICANT |
| Applicant returned to address corrections | 8/31/2023 | GIOVANNY CHAVEZ |
| Applicant returned to address corrections | 10/24/2023 | JESSE ARELLANO |
| Applicant returned to address corrections | 10/24/2023 | CRISTINA SALAZAR |
| Applicant returned to address corrections | 12/14/2023 | DANIEL ABRAMYAN |
| Applicant returned to address corrections | 1/4/2024 | JOSEPH RAFOLS |
| Plan Check Approved | 1/4/2024 | JESSE ARELLANO |
| Issued | 2/8/2024 | APPLICANT |
| CofO in Progress | 5/27/2025 | SEAN HAUPT |
| Permit Finaled | 6/3/2025 | RICHARD STEINBACH |
| CofO Issued | 6/3/2025 | RICHARD STEINBACH |
| Permit Finaled | 6/3/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/13/2023 | DARIN LAM |
| Roof/Waste drainage to street | Cleared | 7/13/2023 | DARIN LAM |
| Grading Pre-Inspection | Cleared | 8/31/2023 | HAYATO TSUCHIYA |
| Miscellaneous | Cleared | 8/31/2023 | HAYATO TSUCHIYA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Biedenbach,, Christopher James; Lic. No.: C74003 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| CARLOS MATAMOROS, (310) 914-3878 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/30/2024 | Not Ready for Inspection | SEAN HAUPT |
| FLOOD-Proofing Certificate | 4/30/2024 | Not Ready for Inspection | SEAN HAUPT |
| Grounding or Bonding | 4/30/2024 | Approved | SEAN HAUPT |
| Pool Piping | 4/30/2024 | Approved | SEAN HAUPT |
| Pre-Gunite | 4/30/2024 | Not Ready for Inspection | SEAN HAUPT |
| Pre-Inspection | 4/30/2024 | Not Ready for Inspection | SEAN HAUPT |
| Rough-Electrical | 4/30/2024 | Approved | SEAN HAUPT |
| Rough-Plumbing | 4/30/2024 | Approved | SEAN HAUPT |
| Special/Order Compliance | 5/1/2024 | Corrections Issued | MICHAEL PELHAM |
| Excavation/Setback/Form/Re-Bar | 5/16/2024 | Approved | SEAN HAUPT |
| FLOOD-Proofing Certificate | 5/16/2024 | Approved | SEAN HAUPT |
| Pre-Gunite | 5/16/2024 | Approved | SEAN HAUPT |
| Pre-Inspection | 5/16/2024 | Partial Approval | SEAN HAUPT |
| Deputy Shotcrete | 5/22/2024 | Approved | SEAN HAUPT |
| Gas Piping or Gas Test | 6/4/2024 | Not Ready for Inspection | STEPHANIE SWANSON |
| Rough-Electrical | 6/4/2024 | Not Ready for Inspection | STEPHANIE SWANSON |
| Gas Piping or Gas Test | 6/10/2024 | Partial Approval | MICHAEL PELHAM |
| Rough-Electrical | 6/10/2024 | Partial Approval | MICHAEL PELHAM |
| Deck | 6/28/2024 | Approved | SEAN HAUPT |
| Enclosure/Fence | 7/12/2024 | Approved | SEAN HAUPT |
| Pool Equipment Noise Test | 4/24/2025 | Approved | ROBERT CHAVEZ |
| SGSOV-Seismic Gas S/O Valve | 4/29/2025 | SGSOV Not Ready | MEL KHACHATOURIAN |
| Final | 4/30/2025 | Corrections Issued | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 4/30/2025 | SGSOV Approved | SEAN HAUPT |
| Final | 5/23/2025 | OK to Issue CofO | SEAN HAUPT |