23938 W JENSEN DR 91304

Certificate Information: 23938 W JENSEN DR 91304

Application / Permit
23047-20000-00954
Plan Check / Job No.
B23VN07768
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
eplan Construct New Swimming Pool Per Standard pool # 268
Permit Issued
Issued on 7/13/2023
Issuing Office
Current Status
CofO Issued on 6/6/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/13/2023 APPLICANT
Assigned to Plan Check Engineer 6/15/2023 RAHEL BEYENE
Corrections Issued 6/20/2023 RAHEL BEYENE
Quality Review Completed 6/29/2023 MICHAEL PEREZ
Plan Check Approved 7/11/2023 RAHEL BEYENE
Issued 7/13/2023 APPLICANT
CofO in Progress 5/23/2024 JEFFREY HARTLINE
CofO in Progress 5/30/2024 HORACE FULTZ
CofO in Progress 5/30/2024 JEFFREY HARTLINE
Permit Finaled 6/6/2024 JOHN JANSON
CofO Issued 6/6/2024 JOHN JANSON
Permit Finaled 6/6/2024 JOHN JANSON

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor H Z S Construction; Lic. No.: 1039476-B 1720 E GARRY AVE #229      SANTA ANA, CA 92705
Engineer Lacher,, Todd Lee; Lic. No.: C67656 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/24/2023 Approved CHRIS CHRISTENSEN
Pre-Gunite 9/1/2023 Corrections Issued CHRIS CHRISTENSEN
Excavation/Setback/Form/Re-Bar 9/5/2023 No Access for Inspection DAVID SCANTLIN
Rough-Electrical 9/5/2023 Not Ready for Inspection DAVID SCANTLIN
Rough-Plumbing 9/5/2023 Not Ready for Inspection DAVID SCANTLIN
Pre-Gunite 9/6/2023 Corrections Issued CHRIS CHRISTENSEN
Excavation/Setback/Form/Re-Bar 9/20/2023 Approved CHRIS CHRISTENSEN
Pre-Gunite 9/20/2023 Approved CHRIS CHRISTENSEN
Rough-Electrical 9/20/2023 Not Ready for Inspection CHRIS CHRISTENSEN
Rough-Plumbing 9/20/2023 Partial Approval CHRIS CHRISTENSEN
Pre-Inspection 10/24/2023 Corrections Issued SEAN WIRCH
Gas Piping or Gas Test 11/9/2023 Approved SEAN WIRCH
Pool Equipment Noise Test 11/9/2023 Not Ready for Inspection ALFREDO FLORES
Rough-Electrical 11/9/2023 Approved SEAN WIRCH
Rough-Plumbing 11/9/2023 Approved SEAN WIRCH
Rough-Mechanical 11/13/2023 No Access for Inspection CHRIS CHRISTENSEN
Final 11/15/2023 Not Ready for Inspection CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 11/15/2023 SGSOV Not Ready CHRIS CHRISTENSEN
Deck 11/20/2023 Approved CHRIS CHRISTENSEN
Final 12/5/2023 No Access for Inspection CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 12/5/2023 SGSOV Not Ready CHRIS CHRISTENSEN
ELECTRICAL-Final 2/13/2024 Not Ready for Inspection CHRIS CHRISTENSEN
Final 2/13/2024 Corrections Issued CHRIS CHRISTENSEN
PLUMBING-Final 2/13/2024 Not Ready for Inspection CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 2/13/2024 SGSOV Not Ready CHRIS CHRISTENSEN
Pool Equipment Noise Test 2/21/2024 Approved ALFREDO FLORES
Final 3/1/2024 Corrections Issued JEFFREY HARTLINE
Pool Equipment Noise Test 3/1/2024 Approved ALFREDO FLORES
SGSOV-Seismic Gas S/O Valve 3/1/2024 SGSOV Not Ready JEFFREY HARTLINE
Final 3/8/2024 Corrections Issued JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 3/8/2024 SGSOV Not Ready JEFFREY HARTLINE
Final 4/5/2024 Partial Approval JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 4/5/2024 SGSOV Approved JEFFREY HARTLINE
Special/Order Compliance 5/14/2024 Corrections Issued JEFFREY HARTLINE
Final 5/24/2024 OK to Issue CofO JEFFREY HARTLINE
Enclosure/Fence 5/31/2024 Approved JEFFREY HARTLINE
Enclosure/Fence 6/5/2024 Approved JEFFREY HARTLINE