11749 N GREENWOOD DR 91326
Certificate Information: 11749 N GREENWOOD DR 91326
- Application / Permit
- 23047-20000-00936
- Plan Check / Job No.
- B23VN07595
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW IRREGULAR SHAPED 45'-5" X 31'-7" SWIMMING POOL AND 10' X 8' SPA WITHIN PER STANDARD PLAN #268 AND ENGINEER DETAIL.
- Permit Issued
- Issued on 6/27/2023
- Issuing Office
- Current Status
- CofO Issued on 1/18/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/8/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/13/2023 | JEROME MAGAT PALMA |
| Corrections Issued | 6/14/2023 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 6/16/2023 | APPLICANT |
| Issued | 6/27/2023 | APPLICANT |
| CofO in Progress | 12/7/2023 | STEVEN BACK |
| Permit Finaled | 1/18/2024 | JOHN JANSON |
| CofO Issued | 1/18/2024 | JOHN JANSON |
| Permit Finaled | 1/18/2024 | JOHN JANSON |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 6/14/2023 | JEROME MAGAT PALMA |
| "T" removal | Cleared | 6/21/2023 | ASHLEY RODARTE |
| Miscellaneous | Cleared | 6/21/2023 | ASHLEY RODARTE |
| Miscellaneous | Cleared | 6/21/2023 | ASHLEY RODARTE |
| Miscellaneous | Cleared | 6/21/2023 | ASHLEY RODARTE |
| Miscellaneous | Cleared | 6/21/2023 | ASHLEY RODARTE |
| ZA Case | Cleared | 6/21/2023 | ASHLEY RODARTE |
| ZA Case | Cleared | 6/21/2023 | ASHLEY RODARTE |
Contact Information
| Contractor | Westmod; Lic. No.: 1053685-C53 | 1276 E COLORADO BLVD_SUITE 210 PASADENA, CA 91106 |
| Engineer | Thompson,, Matthew Gregory; Lic. No.: C86051 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 9/8/2023 | Approved | STEVEN BACK |
| Special/Order Compliance | 9/8/2023 | Corrections Issued | STEVEN BACK |
| Deputy Shotcrete | 9/11/2023 | Approved | JEFFREY PARD |
| Grounding or Bonding | 9/15/2023 | Approved | JEFFREY PARD |
| Enclosure/Fence | 11/7/2023 | Corrections Issued | HENRY KIM |
| Enclosure/Fence | 11/9/2023 | Approved | STEVEN BACK |
| Special/Order Compliance | 11/9/2023 | Corrections Issued | STEVEN BACK |
| Enclosure/Fence | 11/14/2023 | No Access for Inspection | STEVEN BACK |
| Equipment Noise Level | 11/17/2023 | Approved | ALFREDO FLORES |
| Pool Equipment Noise Test | 11/17/2023 | Approved | ALFREDO FLORES |
| Excavation/Setback/Form/Re-Bar | 11/22/2023 | Approved | STEVEN BACK |
| Final | 11/22/2023 | Corrections Issued | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 11/22/2023 | SGSOV Approved | STEVEN BACK |
| Final | 11/29/2023 | Not Ready for Inspection | STEVEN BACK |
| Final | 12/7/2023 | OK to Issue CofO | STEVEN BACK |