6932 N ROYER AVE 91307
Certificate Information: 6932 N ROYER AVE 91307
- Application / Permit
- 23047-20000-00886
- Plan Check / Job No.
- B23VN07247
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- (N) 32' X 19' POOL WITH 7' X 8' SPA PER STANDARD PLAN 268 AND ENGINEERED DETAIL#271
- Permit Issued
- Issued on 12/7/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/31/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/2/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/2/2023 | ALEC MOUSAKHANIAN |
| Corrections Issued | 6/2/2023 | ALEC MOUSAKHANIAN |
| Applicant returned to address corrections | 11/29/2023 | KAMYAR EMAMI |
| Applicant returned to address corrections | 12/6/2023 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 12/7/2023 | RAMA DABADGE |
| Issued | 12/7/2023 | APPLICANT |
| CofO in Progress | 5/28/2024 | TROY SANDERS |
| Permit Finaled | 5/31/2024 | JOHN JANSON |
| CofO Issued | 5/31/2024 | JOHN JANSON |
| Permit Finaled | 5/31/2024 | JOHN JANSON |
Permit Application Clearance Information
| Construction near power lines | Cleared | 11/22/2023 | RIDWAN HARDY |
| Construction within easement | Cleared | 11/22/2023 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 12/1/2023 | EDGAR ALCARAZ |
| Watercourse | Cleared | 12/6/2023 | EDGAR ALCARAZ |
Contact Information
| Contractor | Aldan Construction & Remodeling Inc; Lic. No.: 1030243-B | 8549 WILSHIRE BLVD #1458 BEVERLY HILLS, CA 90211 |
| Engineer | Thompson,, Matthew Gregory; Lic. No.: C86051 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/5/2024 | Approved | TROY SANDERS |
| Grounding or Bonding | 1/5/2024 | Partial Approval | TROY SANDERS |
| Pre-Gunite | 1/5/2024 | Approved | TROY SANDERS |
| Rough-Electrical | 1/5/2024 | Approved | TROY SANDERS |
| Rough-Plumbing | 1/5/2024 | Approved | TROY SANDERS |
| Deputy Shotcrete | 1/8/2024 | Approved | JEFFREY PARD |
| Grounding or Bonding | 5/2/2024 | Approved | TROY SANDERS |
| Enclosure/Fence | 5/13/2024 | Approved | TROY SANDERS |
| Final | 5/21/2024 | Not Ready for Inspection | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 5/21/2024 | SGSOV Approved | TROY SANDERS |
| Equipment Noise Level | 5/23/2024 | Approved | ALFREDO FLORES |
| Final | 5/28/2024 | OK to Issue CofO | TROY SANDERS |